Town of Cortlandt|Homeland Towers / Verizon Wireless 52 Montrose Station Road New Tower – Tech Memo
1 International Boulevard, 10th Floor, Suite 1000, Mahwah, NJ 07495-0027
(201) 335-9300
9
Exhibit 1 – Structural Certification Letter (Scherer Design Group, LLC dated
February 8, 2019; 1 pp.), noting design criteria to be used and that the tower will
be designed to accommodate up to four co-locators
Exhibit 2 – Antenna Site FCC RF Compliance Assessment and Report (Pinnacle
Telecom Group dated December 19, 2018; 18 pp.), attesting that the cell site
would comply with FCC health-based criteria should it be approved and
operational (Verizon only; future co-location was not considered).
Exhibit 3 – FCC Licenses (10 pp.)
Exhibit 4 – Alternative Site Analysis (2 pp.) attesting to the fact that there are no
existing towers or other tall structures upon which to co-locate and no viable non-
residentially zoned properties that would meet Verizon’s service needs
Exhibit 5 – Full SEQRA Environmental Assessment Form (dated February 19,
2019; 13 pp. with 4-page attachment indicating there are no wetlands or
waterbodies at the project site, and providing correspondence from SHPO (May
2018) noting no direct or visual effects on historic properties within the Area of
Potential Effects (APE)
Exhibit 6 – RF Report (C Squared Systems LLC dated February 20, 2019; 16 pp.).
• Drive Test data (700 MHz and 2100 MHz), from a November 1, 2017 field
study
• Tables 1 and 2 (and map) inventorying existing and proposed Verizon cell
sites in the site area
• Coverage maps (low band and high band), depicting existing Verizon
coverage in the area
• Coverage maps (low band and high band), depicting existing Verizon
coverage in the area with the proposed site at 52 Montrose Station Road
Site Plan Drawing set (Scherer Design Group, LLC dated February 8, 2019; 10
sheets)
• Review Memorandum to the Planning Board (Town of Cortlandt Department of Technical
Services Engineering Division, dated March 11, 2019; 3 pp.), based on a review of the
February 21, 2019 applicant submittal
• Comment Letter (review of application material) by Center for Municipal Solutions on behalf of
the Town, dated April 19, 2019, and updated October 16, 2019; 16 pp.
• Visual Resource Assessment (Saratoga Associates, dated April 27, 2019; 45 pp.)
o Narrative describing project description, landscape setting, viewshed analysis, scenic
resources and areas of local interest in the vicinity of the proposed site, and the
methodology followed during the May 4, 2019 balloon test
o Listing of and visibility comments for 29 photo viewpoints (VPs) taken during the May
2019 balloon test
o 2 viewshed maps (bare earth and land cover included); 2-mile and 1-mile radius. The
29 VPs are included on these maps.
o Photolog of balloon test VPs (29)
o Photosimulations (7) for the then-proposed lattice tower design (at the initially-
proposed location on the site)
• Review Memorandum to the Planning Board from the Town Department of Technical Services
Engineering Division dated September 25, 2019; 5 pp.
• Tree Survey (Bartlett Tree Experts) dated December 20, 2019; 2 pp. 127 existing trees were
identified and tagged.