- 1 -
Required Items Reference Guide
Background and Tips for using the Guide..........................................2
What you should know about Required Items....................................3
Reviewing Required Items on BISWeb................................................4
Table of Contents for Required Items .................................................7
General Required Items...................................................................... 9
Post-Approval Required Items.......................................................... 44
Helpful Information .............................................................................46
Required Item Comparison Chart......................................................47
Required Items Sorted by “When Required”....................................49
Index..................................................................................................... 52
- 2 -
Background and Tips for using the Guide
What is the Required
Items Reference Guide?
The Required Items Reference Guide is a publication made
available by the NYC Department of Buildings as a courtesy to the
public. The Guide establishes a clear, common standard for when
requirements apply to a particular job filing and how to satisfy each
requirement.
Are any Required Items
not included in the
Guide?
This version of the Guide does not include the Controlled
Inspection Required Items or Builders Pavement Plan (BPP)
Required Items (with one exception). Explanations for those
Required Items will follow in a future edition of the Guide.
How current is the
information in this version
of the Guide?
The information contained in the Guide is only as current as the
date it was published, which appears on the cover of the guide.
The online version of the Guide is continuously updated and
reflects the most current information. It is available at
http://www.nyc.gov/buildings.
Please note: changes and corrections do occur after printing.
Changes and corrections will be reflected in the online version of
the Guide and will not be printed until the next published version
of the Guide is released.
What happens after the
expiration date listed on
the cover?
Most of this version of the Guide will still be current, but check
the online version of the Guide for the most current information.
Because a change to a Required Item may happen at any point,
it is strongly recommended to always review the online version of
the Guide before taking any steps to satisfy a Required Item.
What else can I get from
the Guide?
Over time, the online version of the Guide will also feature a
number of helpful enhancements, such as:
Links to reference information, including Building Code and
Zoning Resolution citations
Forms and other documents that are required to be submitted
Links to web sites for related city agencies
Searching and sorting
What if I find an error in
the Guide?
If you notice an error that needs to be corrected in the Guide, or if
you have any suggestions for the Guide, please notify us at:
customerservice@buildings.nyc.gov
- 3 -
What you should know about Required Items
What is a Required Item?
Required Items indicate what requirements apply to a specific job,
and when they must be satisfied. Every job filing is unique. Scope
of work, location, and other variables determine which
requirements apply.
How does a Required
Item become associated
with a job?
A Required Item is associated with a job through the Buildings
Information System (BIS), a Plan Examiner, or a filing
professional.
Programming in BIS adds the item. BIS automatically adds
certain requirements based upon programming logic following
pre-established business rules. For example, all NB and Alt 1
jobs require Final Construction Signoff.
A Plan Examiner adds the item. During plan exam, the Plan
Examiner determines which requirements apply.
A filing professional selects the item. On professionally
certified jobs, the professional indicates all items that are
required for the particular job on the PC-1 form (checklist for
Professional Certification). That information is then entered
into BIS by the NYC Department of Buildings.
How do I find out what
Required Items are
associated with my
filing?
Follow the steps on the next pages to track Required Items
using BISWeb.
Who can I contact if I
have questions?
If you have any questions, please e-mail us at
customerservice@buildings.nyc.gov or contact your local
borough office. Borough contact inf
ormation is available at
http://www.nyc.gov/buildings
Note The Guide may not
be a complete list of every item
required for a job.
- 4 -
Reviewing Required Items on BISWeb
If you have a property address:
Visit http://www.nyc.gov/buildings
and input the address into the BIS
web query on the home page
If you have a job number
instead of an address,
please skip to the next
page.
Scroll down and click on Jobs/Filings
on the Property Profile Overview
screen
Locate the job number you want to
check Required Items for and click on
that number
You will arrive at “Application
Data” screen
At this point, please skip to the
“Required Items Screen on
BISWeb” to continue
- 5 -
If you have a BIS job number:
Visit
http://www.nyc.gov/buildings
and navigate to BISWeb
Click “Enter
Buildings
Information System”
Then Click “Building
Information Search”
Scroll down to “Job Number” and
enter the job number in the field
provided
Click “GO” when ready
You will arrive at “Application
Data” screen
At this point, please
skip to the “Required
Items Screen on
BISWeb” to continue
- 6 -
Key to Understanding the Required Items Screen on BISWeb
Click “Items Required” to see
the required items list for that
job
A
B
Indicates total number of items
required for job
C
Denotes who can receive
documentation for this item
T: Plan Examiner Only
N: Clerical Staff
D
“PRI TO” denotes when the
documentation is required prior
to: APP: Approval
PER: Permit
SGN: Signoff
E
Required ID: Clerk who entered
the required item
Required Date: The date when
the required item was added to
the job
F
Received ID: Clerk or plan
examiner who received the
required item
Received Date: When the
required item was received
For TR-1 items denotes the
date the “ID of Responsibility”
was received
G
Date Certified: When TR-1
certification was received
H
Waiver: if an “X” appears, that
item is waived for this job
I
For each required item, a blank
space under a column means
that column is not required.
A “___” means that column
needs to be fulfilled for that
item
J
Changes the screen to show
only the items required prior to
the stages checked
K
Changes the screen to show
either all required items or only
open required items
L
Click “Redisplay” to change the
screen for the options selected
in J or K above. Click “Reset”
to reset the options to show all
items when “Redisplay” is
clicked
A
B C
D
E
I
F
G
H
J
K
L
*Denotes item that can only be received by technical staff.
- 7 -
Table of Contents for Required Items
Controlled Inspections and most BPP Required Items are not included
General Required Items................................9
Address: New House Number Approved* .......9
Adult Activity Approval.....................................9
Adult Establishment Approval*........................9
Anti-Harassment Area Checklist ...................10
Applications: Signoff Open Jobs ...................10
Asbestos ACP 7 or 5 or ASB 4* ....................11
Backflow Preventer .......................................11
Boiler (BL) Signoff .........................................12
BPP: Design Commission Approval -
Distinctive Sidewalk* .....................................12
BPP: Other Items ..........................................12
BSA Variance*...............................................13
BSA/CPC Approval*......................................13
Certificate of Occupancy ...............................13
Clinton District: HPD Certificate of Completion
of Lower Income Housing* ............................13
Clinton Special District Anti-Harassment
Checklist........................................................14
Construction (OT) Signoff..............................14
Cost Affidavit: Estimated ...............................14
Cost Affidavit: Actual .....................................14
CPC: Hudson Yards Initial Certification* .......15
CPC: Hudson Yards Final Certification*........15
Curb Cut: Provide Existing Number* .............15
Curb Cut (CC) Signoff ...................................16
Demolition Application...................................16
Demolition Job Signoff ..................................16
Design Commission Approval: City-owned
property*........................................................17
Detector: Carbon Monoxide...........................17
Detector: Smoke............................................18
Dir. 14 ID of Responsibility............................18
ECCCNYS Compliance Statement................18
Electrical Application for Sidewalk Shed
Lighting..........................................................18
Elevator Job Signoff ......................................19
Environmental “E” - DEP Notice to Proceed* 19
Environmental “E” - DEP Notice of
Satisfaction*.................................................. 19
Equipment (EQ) Permits............................... 19
Equipment Use (EUP) Permits ..................... 20
Excavation or Demolition: 5-Day Notice ....... 20
Fee: Adjustment (Scope of Work Changed) . 20
Fee: Civil Penalty for Legalization* ............... 20
Fee: Pay Deferred Fees* .............................. 21
Final Construction Signoff............................. 21
Final Electrical Signoff .................................. 21
Final Elevator Signoff.................................... 21
Final Plumbing Signoff.................................. 21
Final Sewer House Connection Signoff ........ 22
Fire Alarm (FA): FDNY Approval*................. 22
Fire Alarm/Signal System (FA) Signoff ......... 22
Fire Protection Plan (FPP): FDNY Approval* 23
Fire Retardant Treated Wood: FDNY
Certificate* .................................................... 23
Fire Suppression System (FP) Signoff.......... 23
Flood Zone: FEMA Elevation Certificate....... 24
Folder Review............................................... 24
Foreign Government Property: State
Department Letter*........................................ 24
Foundation Plan Approval............................. 24
Foundation Signoff........................................ 24
Fuel Burning (FB) Signoff ............................. 25
Fuel Storage (FS) Signoff ............................. 25
Gasoline Tank Signoff................................... 25
HPD: SRO MD Certificate of No Harassment*25
HPD: Inclusionary Housing Letter* ............... 26
HPD: Inclusionary Housing Eligibility
Certificate* .................................................... 26
Identify the Primary Job (PW1 §16).............. 26
Insurance: Disability...................................... 26
Insurance: Liability ........................................ 27
Insurance: Workers’ Compensation.............. 27
Insurance: Workers’ Comp. Waiver/Affidavit*27
Landmarks Approval*.................................... 28
*Denotes item that can only be received by technical staff.
- 8 -
Landmarks Signoff.........................................29
Local Law 58 of 1987 Waiver*.......................29
Loft Board Certificate*....................................30
Marquee (OT) Signoff....................................30
Masonry Manufacturer’s Statement...............30
Masonry Supplier’s Statement.......................31
Mechanical (MH) Signoff ...............................31
Microfilm: Additional Required.......................31
Microfilm: Initial..............................................31
PC Filing: Applicant/Owner Statements* .......32
Place of Assembly (PA) Signoff.....................32
Plumbing (PL) Signoff....................................32
Restriction: Deed*..........................................33
Restriction: Easement Agreement*................33
Restriction: Restrictive Declaration................34
Scaffold Permit ..............................................34
Self-certify Objections* ..................................35
Septic Installation: DEP Approval..................35
Sewer Connection: DEP SD-1 & SD-2*.........36
Sidewalk Shed Permit....................................36
Site Connection: DEP*...................................36
Site Safety Plan .............................................36
Sprinkler (SP) Signoff ....................................37
Sprinkler/Standpipe Electrical Letter..............37
Standpipe (SD) Signoff..................................37
Steel Affidavit: Preliminary* ...........................37
Steel Affidavit: Final*......................................38
Street: New Name Approved*........................38
Street: Unmapped - Notify Emergency
Agencies*.......................................................38
Street Tree Checklist .....................................38
Street Tree Sign-Off.......................................39
Subdivision Signoff* ......................................39
Survey: Initial.................................................39
Survey: Final .................................................40
Swimming Pool: DEP Approval.....................40
Swimming Pool: DOH Approval ....................40
Tax lot: Tentative Lot Number Issued*..........40
Tax lot: Final Lot Number Issued ..................40
Transit Authority Approval*............................41
Tree Removal: Outside Property Line/Parks
Approval*.......................................................41
Tree Removal: Special Zoning District/CPC
Approval*.......................................................41
Urban Renewal Area: HPD Approval*...........41
US Army Corps of Engineers Approval*........41
Violations: Clear All.......................................42
Water Supply (private): DOH Approval ........42
Waterfront Area Zoning Compliance*............42
Zoning Exhibit I: Certification*.......................42
Zoning Exhibit II: Certification*......................43
Zoning Exhibit III: Description and Ownership
Statement* ....................................................43
Zoning Exhibit IV: Certification*.....................43
Zoning Exhibit V: Certification*......................43
Post-Approval Required Items...................44
Escrow Letter (Attorney)................................44
Escrow Letter (Builder)..................................44
Fee: TCO Payment ($100)............................44
Temp Construction Signoff............................44
Temp Elevator Signoff (Hi-Rise Only) ...........45
Temp Plumbing Signoff - Partial Building......45
Temp Plumbing Signoff - Entire Building.......45
Update Final Construction Signoff.................45
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 9 -
General Required Items
This does not include Controlled Inspections and most BPP Required Items.
Items are sorted alphabetically by item description.
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
1.
Address: New
House Number
Approved*
X
GCL § 35 & 36
Memo: 4/1/83
Select if the application
results in a new house
number.
Each new house number must be
accurately recorded in City records.
Obtain house number verification
stamp on back of PW-1 from
Topographic Unit of Borough
President's Office. Submit stamp
with PW-1.
2.
Adult Activity
Approval
X
ZR §32-01
ZR §42-01
OPPN 7/02, 6/98,
5/98, 8/96, 7/96
Select when filing a
professionally certified
application that includes
adult activity on the
premises.
When proposed use of a premises
involves adult activity, borough
referral to DOB legal for review is
required to ensure that the premises
is not an adult establishment.
Must submit plans for plan exam
approval.
3.
Adult Establishment
Approval*
X
ZR §32-01
ZR §42-01
OPPN 7/02, 6/98,
5/98, 8/96, 7/96
Select when establishing a
new or enlarging an
existing “adult
establishment” use as
defined by ZR §12-10.
For new adult establishments,
borough referral to DOB legal for
review is required to ensure that
Zoning permits the adult
establishment.
Submit zoning plot diagram
showing conformance with ZR.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 10 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
4.
Anti-Harassment
Area Checklist
X
ZR § 93-90
ZR § 98-70
ZR § 121-50
ZR § 23-013
Automatically applies for
NB, A1 (all work types), A2
(PL, OT/GC and OT-Other
work types), A3 (OT/GC
and OT-Other work types),
subdivision, applications
located within Special
Hudson Yards District,
Special West Chelsea
District, Special Garment
Center P-2 Preservation
Area or Greenpoint-
Williamsburg Anti-
Harassment Area.
To preserve affordable housing,
certification from the Department of
Housing Preservation and
Development (HPD) is required to
ensure that development satisfies
legal requirements pertaining to the
eviction and relocation of tenants.
Or the applicant must state if the
proposed work is exempt from these
regulations.
Submit Anti-Harassment Area
Checklist (HPD-1)
If the work is not exempt, submit
HPD Certificate of No Harassment
or HPD Certification of Cure
Compliance
As indicated on the checklist, some
exemptions may require
submission of HPD Determination
5.
Applications:
Signoff Open Jobs
X
BC §26-222
MDL §301.1
NYC Charter
645(b)(3)d
This item will automatically
apply to NB and Alt 1
applications.
Upon issuance of a CO, the
department is certifying that the
building substantially complies with
the Building Code and other laws,
rules, and regulations, including that
no open applications are
outstanding.
Ensure that all open applications
have been signed off.
Note: A pilot project in Manhattan
allows final CO where open
applications exist subject to certain
criteria and limitations.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 11 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
6.
Asbestos ACP 7 or 5
or ASB 4*
X
LL 76/85
BC §27-198.1
AC §24-146.1
TPPN 2/87
OPPN 1/87,
10/87, 1/88, 4/88,
3/89, 17/89,19/90,
17/91, 9/93, 24/88
Select for all Alt 1, Alt 2 and
Alt 3 jobs, except Alt 1 jobs
for legalization of
demolition work completed
prior to April 1, 1987.
An asbestos report is required to
ensure that alteration work proposed
under this application complies with
the Asbestos Certification and
Containment Law (Local Law 76/85),
§27-198.1, and §24-146.1 (Dept of
Environmental Protection
regulations).
The ACP 7 report is required for any
friable “asbestos project.” The ACP
5 report is required for any friable
non-“asbestos project.” The ASB 4
report is required for any project
claiming an exemption from
asbestos certification.
Submit ACP 7 if asbestos-
containing material, exceeding 10
sq. ft. or 25 linear feet, is to be
removed; AND submit proof of
payment receipt from DEP.
Submit ACP 5 if no asbestos-
containing material is disturbed
exceeding 10 sq. ft. or 25 linear
feet.
Submit ASB 4 if the work is exempt
from filing ACP 7 or ACP 5.
7.
Backflow Preventer
(RPZ or Double-
Check Valve
Assembly)
X
RS 16, §107.18(5)
LL 67/77
OPPN 14/90
NYS Sanitary
Code 5-1.31
Select for all NB, Alt 1, Alt 2
applications and ARA’s
where the proposed work
involves a) a new
connection to public water
supply or b) installation of a
new sprinkler system or
any other device that might
cause a threat to the
potable water system.
Approval from the Dept of
Environmental Protection (DEP) for
installation of an RPZ or double-
check valve is required to prevent
contamination of the potable water
supply.
Have device tested and obtain a
Gen. 215B form (RPZ test letter)
signed by the Testing Contractor
and Plumber and signed and
sealed by the PE or RA.
Submit to Plumbing Division.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 12 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
8.
Boiler (BL) Signoff
X
BC §27-793
OPPN 6/93
LL 62/91
Select this item if the NB or
Alt 1 application has a
boiler (BL) application that
is filed under a separate
job number.
If filed separately from the main
application, the boiler (BL)
application must be signed off to
insure proper installation of a large
boiler (boiler rating higher than
350,000 BTU) to ensure that they
were installed safely.
File PW-1C (Schedule C).
On the PW-1 for the BL application,
identify the job number of the
related NB/Alt 1 in Sec. 16 or Part
A of Sec. 7.
Obtain BL signoff from Boiler
division and provide letter of
completion.
9.
BPP: Design
Commission
Approval -
Distinctive
Sidewalk*
X
NYC Charter
§854(b) & (e)
LL77/95
DOB Dir. # 2/78
Select for all BPP
applications on city-owned
property that deviate from
standard concrete color or
scoring pattern 5' x 5'
and/or add/alter exterior
walls or structures,
including but not limited to
fences, gates, steps,
curbing, distinctive paving,
benches, lamps, posts,
signage, traffic signals or
other similar structures on
city-owned property.
Approval from the Design
Commission is required to ensure
that work proposed receives
aesthetic merit.
Obtain Design Commission
Certificate of Approval.
Submit to Plan Examiner.
10. BPP: Other Items Please note: all Builders Pavement Plan Required Items are not listed in the Guide. Additional BPP Required Items will be incorporated in future
editions of the Guide.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 13 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
11.
BSA Variance*
X
ZR §72-21
ZR §32-31
ZR §32-32
NYC Charter
666.6 & 666.7
MDL §310
Select for any application
where the proposed work
would be prohibited by
Zoning Res., Admin. Code
or MDL.
If work proposed under this
application does not comply with
Zoning Res., Admin Code, or MDL,
DOB may permit such work or
development only if applicant
obtains a variance from the Board of
Standards and Appeals (BSA).
Obtain objection from plan
examiner or other appropriate
party.
Obtain variance from BSA.
Indicate calendar number and
conditions of approval on Schedule
A.
12.
BSA/CPC Approval*
X
ZR § 72-21
ZR § 32-31
ZR § 32-32
OPPN 16/87
Select for any application
where the proposed work
requires a special permit,
authorization, or
modification by the BSA or
by the CPC.
If the proposed work requires a
special permit or authorization
pursuant to the ZR, DOB may permit
such work if applicant obtains
approval from the BSA and/or the
CPC.
Obtain approvals from BSA and/or
CPC.
Indicate calendar number and
conditions of approval on Schedule
A.
13.
Certificate of
Occupancy
X
BC §27-213, 217
OPPN 6/93
This item will automatically
apply to NB and Alt 1
applications.
The Certificate of Occupancy (CO)
is an official legal document, which
states the permissible use and
occupancy of the premises.
Submit CO Application (PW-6) to
CO Unit.
14.
Clinton District:
HPD Certificate of
Completion of
Lower Income
Housing*
X
ZR § 96-110(d)
(2)(ii)
Select for all A1 or NB jobs
located on a cure
requirement lot (other than
any Lower Income Housing
located on such cure
requirement lot)
To preserve affordable housing, the
Department of Housing Preservation
and Development (HPD) requires
that the affordable housing required
by the Clinton District restrictive
declaration to be completed in
compliance with the restrictive
declaration and that a temporary or
final certificate of occupancy has
been issued for each unit of the low-
income housing.
Provide proof of temporary or final
certificate of occupancy indicating
CFRN Numbers and occupancy
restrictions for all low-income
housing and for all other tax lots on
the Cure Requirement Lot.
HPD Certification of Completion of
Lower Income Housing
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 14 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
15.
Clinton Special
District Anti-
Harassment
Checklist
X
ZR § 96-00
ZR § 96-10
ZR § 96-108
ZR § 96-109
ZR § 96-110
ZR § 96-20
Automatically applies for
NB, A1 (all work types), A2
(PL, OT/GC and OT-Other
work types), A3 (OT/GC
and OT-Other work types),
subdivion, applications
located within Clinton
Special District.
To preserve affordable housing,
certification from the Department of
Housing Preservation and
Development (HPD) is required to
ensure that development satisfies
legal requirements pertaining to the
eviction and relocation of tenants.
Or the applicant must state if the
proposed work is exempt from these
regulations.
Clinton Special District Anti-
Harassment Checklist (HPD-2)
If the work is not exempt, submit
HPD Certificate of No Harassment,
HPD Certification of Cure
Compliance, or CPC Special
Permit
As indicated on the checklist, some
exemptions may require
submission of HPD Determination
16.
Construction (OT)
Signoff
X
BC §27-156 Select this item if the NB or
Alt 1 application has a
“other construction” (OT)
application that is filed
under a separate job
number.
If filed separately from the main
application, a construction (OT)
application must be signed off to
ensure that related general
carpentry and construction work was
performed safely and complies with
Code.
File OT work type.
On the PW-1 for the OT
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain OT signoff from
Construction division or provide
letter of completion for OT
application.
17.
Cost Affidavit:
Estimated
X
Select for Alt 1, Alt 2 and
Alt 3 applications.
A cost affidavit indicating estimated
costs is required to ensure
appropriate assessment of DOB
fees.
Contractor to submit cost affidavit
form (PW-3) indicating estimated
cost of construction.
18.
Cost Affidavit:
Actual
X
Select for Alt 1 applications
only.
A cost affidavit indicating actual
costs is required to ensure
appropriate assessment of DOB
fees.
Submit original, typed, notarized
final owner’s cost affidavit form
(PW-3) to fee estimator.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 15 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
19.
CPC: Hudson Yards
Initial Certification*
X
ZR § 93-31 Select for NB and Alt 1
applications where
additional floor area is
proposed pursuant to
Hudson Yards District
Improvement Bonus.
In the Hudson Yards District,
maximum floor area may be
increased provided that an
acceptable contribution, certified by
CPC, be deposited into the Hudson
Yards District Improvement fund or
adequate security for such deposit
be provided.
Provide an original letter from CPC
that certifies a contribution of funds
has been made or will be secured
for the Hudson Yards District
Improvement Fund.
The letter must specify the square
footage of the development rights
yielded by the Hudson Yards
District Improvement Bonus.
20.
CPC: Hudson Yards
Final Certification*
X
ZR § 93-31 Select for NB and Alt 1
applications where
additional floor area is
proposed pursuant to
Hudson Yards District
Improvement Bonus.
In the Hudson Yards District,
maximum floor area may be
increased provided that an
acceptable contribution, certified by
CPC, has been deposited into the
Hudson Yards District Improvement
fund.
Provide an original letter from CPC
that certifies a full contribution has
been made into the Hudson Yards
District Improvement Fund.
If a full contribution was made prior
to application approval the Plan
Examiner may use the original
CPC letter already provided to
waive this item.
21.
Curb Cut: Provide
Existing Number*
X
BC §27-480
ZR §25-63,
25-631 and 632,
§36-53, 36-682,
44-43, 44-582
Select if the application
proposes use of an existing
legal curb cut.
Curb cut application numbers must
be identified to ensure that existing
curb cuts are legal.
Identify existing curb cut job
number on the new plans.
For pre-BIS jobs, indicate DOB
identification number on plans.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 16 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
22.
Curb Cut (CC)
Signoff
X
BC §27-480
ZR §13-142(a)
Select this item if the NB or
Alt 1 application has a curb
cut (CC) application filed
under a separate
job
number. Requirement does
not apply to applications
reusing an existing legal
curb cut.
If filed separately from the main
application, the curb cut (CC)
application must be signed off to
ensure that new curb cuts and
modifications to existing curb cuts
(to provide access to off-street
parking) are registered and comply
with size and location controls.
File CC application.
On the PW-1 for the CC
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain all required Department of
Transportation permits.
Provide letter of completion.
23.
Demolition
Application
X
OPPN 6/90,
12/92, 9/93, 6/90,
24/87, 24/89,
10/92
This item will automatically
apply to all NB applications.
In order to construct a new building
on improved property, the existing
structure must be demolished
Submit application for demolition of
existing structure or seek waiver of
requirement if property is not
improved.
24.
Demolition Job
Signoff
X
OPPN 6/90,
12/92, 9/93, 6/90,
24/87, 24/89,
10/92
This item will automatically
apply to all NB applications.
If an application to perform
demolition work is filed, the job must
be signed off to ensure that the
demolition work was completed
properly.
BIS system must reflect demolition
job in “X” status (signed off).
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 17 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
25.
Design Commission
Approval: City-
owned property*
X
NYC Charter
§854(b) & (e)
LL77/95
DOB Dir. # 2/78
Select for NB jobs located
on city-owned property
where structure meets
qualifications set forth in
NYC Charter, Chapter 37,
Section 854(b).
Select for alterations to
existing structure located
on city-owned property
when alteration affects
exterior walls or structures,
including fences, gates,
steps, curbing, distinctive
paving, benches, lamps,
posts, signage, traffic
signals or other similar
structures on city own
property.
Approval from the Design
Commission is required to review for
aesthetic merit.
Obtain Design Commission
Certificate of Approval.
Submit to Plan Examiner.
26.
Detector: Carbon
Monoxide
X
BC §27-981.2
1 RCNY §28-02
RS 17-13, 17-14
Select for all NB, Alt 1, Alt 2
and Alt 3 jobs where
carbon monoxide detectors
are required to be installed
as a result of the work
being performed.
Most dwelling units and buildings in
occupancy group G (educational) or
H-2 (institutional) are required to
have detectors.
Indicate location of carbon
monoxide detectors on plans.
Where permitted to be battery-
operated, submit a notarized
affidavit signed by the owner.
Where required to be hardwired,
submit letter from electrician or
P.E/R.A. indicating compliance.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 18 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
27.
Detector: Smoke
X
BC §27-978 - 27-
981
1 RCNY §28-01
RS 17-11, 17-12
Select for all NB, Alt 1, Alt 2
and Alt 3 jobs where smoke
detectors are required to be
installed as a result of the
work being performed.
Most residential buildings are
required to have smoke detectors for
fire safety. Requirements vary by
building type.
Indicate location of smoke
detectors on plans.
Where permitted to be battery-
operated, submit a notarized
affidavit signed by the owner.
Where required to be hardwired,
submit letter from electrician or
P.E./R.A. indicating compliance.
28.
Dir. 14 ID of
Responsibility
X
Dir. 14, 1975 This item will automatically
apply to D14 applications
with work type MH, EQ, CC
or OT.
When submitting applications via
Dir. 14, 1975, applicant must notify
DOB who will be responsible for final
inspection.
Submit TR-1 indicating the
individual responsible for final
inspection.
29.
ECCCNYS
Compliance
Statement
X
Energy
Conservation
Construction Code
of New York State
This item will automatically
apply to all New Building
(NB) applications.
When submitting an application,
applicants must demonstrate
compliance with the Energy
Conservation Construction Code of
New York State.
Place appropriate statement of
compliance or reason for
exemption on plans.
30.
Electrical
Application for
Sidewalk Shed
Lighting
X
BC §27-1021
LL 33/91
This item automatically
applies to all sidewalk shed
applications.
Only a licensed electrician can
install the lighting required for a
sidewalk shed.
Provide either: a) copy of an active
electrical permit to install sidewalk
shed lighting or b) copy of a
BISWeb print out of an accepted
electrical application to install
sidewalk shed lighting.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 19 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
31.
Elevator Job Signoff
X
BC §24-147 Select this item if the NB or
Alt 1 application involves
elevator work.
When an application to perform
elevator work is filed, the elevator
job must be signed off to ensure the
elevator work was completed
properly.
Obtain Elevator job signoff from
Elevator division or provide letter of
signoff.
32.
Environmental “E” -
DEP Notice to
Proceed*
X
ZR §11-15
ZR § 93-051
ZR § 98-051
ZR § 104-05
ZR § 115-03
OPPN 2/05
Select for NB, Alt 1, Alt 2
and Alt 3 applications
where work is to be
performed on a lot
designated with an “E” on
the Zoning Map.
DEP must approve proposed work
that falls within the scope of ZR §§
11-15, 93-051, 98-051, 104-05 or
115-03 to ensure that all
environmental requirements have
been met or will be met upon
completion of the work.
Submit either: DEP Notice to
Proceed, or DEP Notice of No
Objection, or Statement on AI-1
form describing why the proposed
work falls outside of the scope of
ZR §§ 11-15, 93-051, 98-051, 104-
05 or 115-03
33.
Environmental “E” -
DEP Notice of
Satisfaction*
X
ZR §11-15
ZR § 93-051
ZR § 98-051
ZR § 104-05
ZR § 115-03
OPPN 2/05
Select for NB, Alt 1, Alt 2
and Alt 3 applications that
receive approval upon
submission of a DEP
Notice to Proceed.
DEP must approve all work
completed pursuant to a Notice to
Proceed to ensure that the
completed work satisfies
environmental requirements.
Submit DEP Notice of Satisfaction.
34.
Equipment (EQ)
Permits
X
BC §27-1001
Memo 4/12/76
Select for all applications
where construction-related
equipment will be used on-
site.
Equipment permits are required for
construction fences, certain
scaffolds and other construction-
related equipment to ensure safe
operation.
Identify equipment types on PW-1.
Obtain permits for equipment.
Inspection may be required.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 20 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
35.
Equipment Use
(EUP) Permits
X
BC §27-185 and
27-190
Select for all applications
where service equipment or
systems indicated in §27-
185 are or will be installed.
Equipment use permits are required
for operation of service equipment or
systems, such as HVAC equipment
and systems, elevators, fuel burning
and fuel-oil storage, and certain
boilers.
Identify equipment types on PW-4.
Obtain plan approval from plan
examiner or PE/RA on file.
Construction inspector or applicant
must sign all equipment use
permits.
If AC unit will be operated, file AC
equipment use card for tonnage
generated.
36.
Excavation or
Demolition: 5-Day
Notice
X
BC §27-165 and
27-169
Memo 10/19/88
Select if the application
involves excavation,
earthwork, or demolition.
When excavation, earthwork or
demolition is to occur, written
notification to all adjoining property
owners is required at least five days
prior to permit application. Additional
written notice is required prior to
commencement of work.
Submit certified mail receipts and
copies of letters sent to owners of
adjoining lots at time of initial
permit application.
37.
Fee: Adjustment
(Scope of Work
Changed)
X
AC §26-210 and
§26-211
OPPN 2/97 & 4/99
Select if filing an
amendment or correction of
a post-approval
amendment and scope of
work has changed from
that originally submitted.
When scope of work changes, a fee
assessment is required that may
result in additional fees. Payment of
the additional fees is required prior
to approval of the initial job or if a
PAA, prior to approval of the PAA.
See plan examiner and pre-filer for
determination of new fees.
Pay fees at Cashier.
38.
Fee: Civil Penalty
for Legalization*
X
LL 58/88 Select if legalizing work
done after 1989 without a
valid permit
DOB issues civil penalties if work
was done after 1989 without a
permit. Work done without a permit
before 1989 is exempt from civil
penalties.
See Fee Estimator
Pay civil penalty fee at Cashier.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 21 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
39.
Fee: Pay Deferred
Fees*
X
Memo 5/2/86 and
9/26/84
OPPN 2/94
APPN 1/93
Select if property qualifies
for fee deferral; certain
properties are eligible as
per APPN #1/93.
If the city or a tax-exempt institution
owns the property, the applicant
may defer payment of fees until
signoff when City properties are
transferred to private ownership.
Pay fee at Cashier prior to seeking
CO (temporary and final).
40.
Final Construction
Signoff
X
BC §27-210 This item will automatically
apply to NB and Alt 1
applications.
A signoff from the Construction
Division is required to ensure that
completed work passes DOB’s
Construction inspection.
Schedule Construction inspection.
Obtain signoff.
41.
Final Electrical
Signoff
X
BC §27-210 This item will automatically
apply to NB and Alt 1
applications.
A signoff from the Bureau of
Electrical Control is required to
ensure that completed work passes
DOB’s Electrical inspection.
Schedule Electrical inspection.
Obtain signoff.
42.
Final Elevator
Signoff
X
BC §27-210 This item will automatically
apply to NB and Alt 1
applications.
A signoff from the Elevator Division
is required to ensure that completed
work passes DOB’s Elevator
inspection.
Schedule Elevator inspection.
Obtain signoff.
43.
Final Plumbing
Signoff
X
BC §27-210 This item will automatically
apply to all NB and Alt 1
applications and Alt 2
applications with a PL work
type.
A signoff from the Plumbing Division
is required to ensure that completed
work passes DOB’s Plumbing
inspection.
Schedule Plumbing inspection or
conduct self-certified inspection.
Obtain signoff.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 22 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
44.
Final Sewer House
Connection Signoff
X
LL 65/96 Select for all applications
requiring a connection to
the city sewer system.
This item will automatically
apply to NB applications.
A final sewer house connection
signoff is required for new sanitary,
storm or combined sewer
connections. DOB should waive the
requirement if a septic system is, or
will be, installed.
Obtain a satisfactory inspection
from a Buildings inspector, or
Obtain a satisfactory inspection
from a DEP inspector and present
a copy of the DEP Sewer Card to
the Buildings’ Plumbing Unit
45.
Fire Alarm (FA):
FDNY Approval*
X
OPPN 3/91
TPPN 2/89
Memo 3/9/84,
1/22/83
1 RCNY §28-02
(e)(2)
Select if the application is a
fire alarm work type except
if filing per Dir. 14/75 for
mini class E, cabaret or
carbon monoxide detector
systems.
A letter of approval from the FDNY
Bureau of Fire Prevention for a Fire
Alarm (FA) work type is required to
ensure that the FA application has
met FDNY standards.
Obtain a letter of approval from
FDNY Bureau of Fire Prevention
per procedures outlined in OPPN
3/91.
46.
Fire Alarm/Signal
System (FA) Signoff
X
BC §27-968 &
981.2
OPPN 3/91
Select this item if the NB or
Alt 1 application has a fire
alarm/signal system (FA)
application that is filed
under a separate
job
number.
If filed separately from the main
application, the alarm/signal/CO
detector system (FA) application
must be signed off to ensure that the
system was properly installed;
required for certain building types
and/or occupancy.
File FA application with DOB.
On the PW-1 for the FA application,
identify the job number of the
related NB/Alt 1 in Sec. 16 or Part
A of Sec. 7.
Obtain FDNY approval letter prior
to DOB approval.
Obtain FA application signoff from
FDNY and provide letter of
completion.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 23 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
47.
Fire Protection Plan
(FPP): FDNY
Approval*
X
Dir. 1/81
BC §27-228.1 and
§27-228.2
Memo 12/5/86
OPPN 8/89
LL 16/84 & 5/73
For the types of buildings
listed in BC §27-228.1,
select for all NB and any
alteration application
involving change in use,
exceeding $1 million in cost
or resulting in amendments
to a previously issued Fire
Protection Plan.
A fire protection plan is describes
the key fire protection features of a
building.
Submit Fire Protection Plan to
FDNY and DOB.
Submit FDNY letter of approval to
DOB.
48.
Fire Retardant
Treated Wood:
FDNY Certificate*
X
Dir. 20/71
Memo 3/27/72
and 10/19/89
BC §27-328
Select if the application
involves the use of fire-
retardant treated wood.
A fire-retardant treated wood
certificate is required to ensure that
the wood used in work under this
application has been certified to
maintain a fire rating.
Obtain a fire-retardant treated
wood certificate from FDNY.
49.
Fire Suppression
System (FP) Signoff
X
BC §27-232 Select this item if the NB or
Alt 1 application has a fire
suppression system (FP)
application that is filed
under a separate
job
number.
If be filed separately from the main
application, the fire suppression
system (FP) application must be
signed off to ensure that it was
properly installed for cooking
equipment.
The FP application must distinguish
between class A (water source) and
class C (chemical source) systems.
File FP application with DOB.
On the PW-1 for the FP application,
identify the job number of the
related NB/Alt 1 in Sec. 16 or Part
A of Sec. 7.
Identify related mechanical work
type.
Obtain FP application approval
from FDNY and submit to DOB to
obtain letter of completion.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 24 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
50.
Flood Zone: FEMA
Elevation Certificate
X
BC §27-316(g)
TPPN 1/04
Select for all NB and any
alterations that are a
substantial improvement
where the property is
located in a flood zone.
An elevation certificate from FEMA
is required to assure that
construction in a flood zone meets
FEMA standards.
Have P.E./R.A. certify elevation
using a FEMA elevation certificate.
Submit to DOB
51.
Folder Review
X
This item will automatically
apply to NB and Alt 1
applications.
Before a Certificate of Occupancy is
issued, the department must insure
that all requirements have been
complied with.
Obtain all necessary signoffs.
Submit job folder with proper
documentation to CO Unit
52.
Foreign
Government
Property: State
Department Letter*
X
TPPN 5/94 Select for NB, Alt 1, Alt 2 or
Alt 3 jobs involving property
owned by a foreign
government.
Approval from the US State Dept is
required when work involves
property owned by a foreign
government.
Submit letter of no objection from
Office of Foreign Missions of the
US Dept. of State.
53.
Foundation Plan
Approval
X
BC §27-163 Select this item if the NB or
Alt 1 application has a
foundation plan.
Foundation plans are required to
ensure that work done to a
foundation is properly completed.
File application for foundation work.
Obtain plan approval.
54.
Foundation Signoff
X
BC §27-163 Select this item if the NB or
Alt 1 application has a
foundation plan.
Foundation plans are required to
ensure that work done to a
foundation is properly completed.
Obtain OT application signoff from
Construction Division and provide
letter of completion.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 25 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
55.
Fuel Burning (FB)
Signoff
X
Memo 6/7/72 and
10/31/72
Select this item if the NB or
Alt 1 application has a fuel
burning (FB) application
that is filed under a
separate
job number.
If filed separately from the main
application, a signed off fuel burning
(FB) application is required to
ensure that fuel burning equipment
was properly installed.
File FB application.
On the PW-1 for the FB application,
identify the job number of the
related NB/Alt 1 in Sec. 16 or Part
A of Sec. 7.
Obtain FB application signoff and
provide letter of completion.
56.
Fuel Storage (FS)
Signoff
X
OPPN 7/94
Select this item if the NB or
Alt 1 application has a fuel
storage (FS) application
that is filed under a
separate
job number.
If filed separately from the main
application, a signed off fuel storage
(FS) application is required to
ensure that DOB has authorized fuel
storage on the premises.
File FS application.
Obtain FS application signoff from
Boiler Division and FDNY to get
letter of completion.
57.
Gasoline Tank
Signoff
X
BC §27-440
LL 68/99
TPPN 6/00
Select this item if the NB or
Alt 1 application has a
gasoline tank (for
installation or modification)
that is filed under a
separate
job number.
If filed separately from the main
application, a signed off gasoline
tank application is required to
ensure that DOB has authorized
placement of a gasoline tank on the
premises.
File gasoline tank application with
FDNY and DOB.
Submit approval letters from NYS
Dept of Environmental
Conservation (DEC) and NYC Dept
of Environmental Protection.
58.
HPD: SRO MD
Certificate of No
Harassment*
X
BC §27198
28 RCNY §10-
03(a)(1)
AC 27-2093(e)
Select for every alteration
or demolition application
where the building is a
“single room occupancy
multiple dwelling”.
If the property is a single-room
occupancy (SRO) multiple dwelling,
a certification, waiver, or letter
exempting work from (HPD) is
required.
Submit Certification or Waiver, or
letter exempting work from HPD.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 26 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
59.
HPD: Inclusionary
Housing Letter*
X
ZR § 23-90
ZR § 23-95(f)
Select for all Compensated
Development jobs (jobs
that are eligible for an
increased floor area ratio
pursuant to HPD’s
Inclusionary Housing
Program).
To preserve affordable housing, no
building permit for a Compensated
Development job will be issued until
an acceptable Lower Income
Housing Plan is filed, approved and
certified by HPD.
Provide letter from HPD that
certifies that the Lower Income
Housing Plan has been submitted
and approved. Letter specifies the
square footage of the Floor Area
Development Rights yielded by the
Lower Income Housing.
60.
HPD: Inclusionary
Housing Eligibility
Certificate*
X
ZR § 23-90
ZR § 23-95(f)
Select for all Compensated
Development jobs (jobs
that are eligible for an
increased floor area ratio
pursuant to HPD’s
Inclusionary Housing
Program).
To preserve affordable housing, no
temporary or final certificate of
occupancy can be issued until HPD
certifies that the Lower Income
Housing is complete and in
compliance with the Lower Income
Housing Plan.
Provide original certified and
completed copy of HPD’s
“Inclusionary Housing Program
Certificate of Eligibility for Zoning
Bonus” containing HPD’s
embossed seal.
61.
Identify the Primary
Job (PW1 §16)
X
BC § 27-147
BC § 27-156
Select for any job if an
active NB or Alt 1
application exists for the
property.
When filing multiple applications for
a single project, the applicant must
identify the primary/master NB or Alt
1 job on each of the related job
filings.
Identify the job number of the
primary/master job (NB/Alt1) in
Section 16 of PW-1 for the related
job filing.
62.
Insurance: Disability
X
BC § 27-160 This item will automatically
apply to all applications
except subdivisions.
Disability insurance which covers
the contractor and contractor’s
employees is required for all jobs
except “no work” permit types and
owner-pulled permits
Submit DB 120.1 form or waiver
form WC/DB-100.
Submit contractor tracking number
(if active)
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 27 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
63.
Insurance: Liability
X
BC §27-204(b)
BC §27-160
NYC Charter 2-20
OPPN 6/92
This item will automatically
apply to all applications
except subdivisions.
Liability insurance which covers the
contractor and contractor’s
employees is required.
Submit ACORD form completed by
a licensed insurance broker
showing policy number and
effective date and DOB as
certificate holder.
Submit contractor tracking number
(if active)
64.
Insurance: Workers’
Compensation
X
BC §27-160 This item will automatically
apply to all applications
except subdivisions.
Workers’ Compensation insurance is
required. DOB may waive the
requirement for applications
involving legalization or no work, or
work performed by the homeowner.
Submit DB 120.1 form
Submit a C106.2, GSA 105.2, SI
12, or U26.3 form. See Contractor's
Insurance Requirement sheet in
the Borough Office to verify form.
Submit contractor tracking number
(if active)
65.
Insurance: Workers’
Comp.
Waiver/Affidavit*
X
BC §27-160 Select this item if
submitting a waiver/affidavit
for Worker’s Compensation
insurance
Workers’ Compensation insurance is
required. DOB may waive the
requirement for applications
involving legalization or no work, or
work performed by the homeowner.
Submit waiver form WC/DB-100
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 28 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
66.
Landmarks
Approval*
X
Memo 1/7/76 and
7/6/88
TPPN 10/88
OPPN 19/88
OPPN 13/88
AC §25-301-321
1 RCNY
§ 21-01(d)
Select for all applications
where the property is an
individually landmarked
structure or is located
within a landmarked district
or contains a designated
interior that is landmarked.
Approval from the Landmarks
Preservation Commission (LPC) is
required to ensure that work
proposed under this application
does not affect property with a
landmarks designation.
Submit to DOB drawings approved
and perforated by LPC and either a
“Permit: Certificate of No Effect” or
“Permit: Certificate of
Appropriateness,” or describe how
the proposed work is exempted
from LPC review pursuant to Memo
1/7/76.
Notes:
For Alt 2 or Alt 3: LPC requires BIS
job # prior to LPC approval
For NB or Alt 1: LPC requires BIS
job # and objection sheet (if
applicable) prior to LPC filing
All zoning objections must be
satisfied prior to filing with LPC
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 29 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
67.
Landmarks Signoff
X
Memo 1/7/76 and
7/6/88
TPPN 10/88
OPPN 19/88
OPPN 13/88
AC §25-301-25-
321
1 RCNY
§ 21-01(d)
Select if the “Permit:
Certificate of
Appropriateness” issued by
LPC requires a Landmarks
inspection signoff as a
condition.
DOB requires that the work be
inspected and signed off by the
Landmarks Preservation
Commission (LPC) when LPC
places such a condition in the
“Permit: Certificate of
Appropriateness.”
Submit LPC signoff to DOB.
Submit “Permit: Certificate of No
Effect” to have this item waived.
68.
Local Law 58 of
1987 Waiver*
X
BC §27-292.6
LL 58/87
Select for all applications
seeking waiver of
compliance with LL 58/87.
Existing buildings that are unable to
comply with accessibility
requirements of the Code may apply
for a waiver as set forth in BC §27-
292.6.
Obtain advisory opinion from
Mayor’s Office for People with
Disabilities (MOPD).
Obtain Borough Commissioner
determination that waiver will be
granted.
Submit PEO-1 form.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 30 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
69.
Loft Board
Certificate*
X
MDL §284(1)(v)
29 RCNY §1-06:1,
2-01(1), (h), (o),
(m)
Select for Alt 1, Alt 2 or
Alt 3 applications where the
building is designated an
Interim Multiple Dwelling
(IMD) building by the Loft
Board.
Loft Board certificate is required for
alteration of a registered Interim
Multiple Dwelling (IMD) building.
Check the Loft Board website for a
list of IMD buildings or the BIS
Property Profile for LOFT
designation.
Submit Loft Board certificate.
Applicant must resolve all DOB
objections prior to seeking Loft
Board certificate.
70.
Marquee (OT)
Signoff
X
AC §26-207,
§26.214(6) and
§27-504, 313
Select this item if the NB or
Alt 1 application has a
marquee (OT) application
that is filed under a
separate job number.
If filed separately from the main
application, a signed off marquee
(OT) application is required to
ensure that the marquee was
installed properly.
File marquee application.
On the PW-1 for the marquee
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain marquee application signoff
from Construction Division or
provide letter of completion.
71.
Masonry
Manufacturer’s
Statement
X
BC §27-600
RS 10-1 & 10-2
Table 10-1 fn “c”
Select if the application
proposes the installation of
structural masonry.
A manufacturer's statement is
required to ensure that masonry
proposed for use meets quality
standards and is in compliance with
A.S.T.M. requirements.
Submit a 10H form.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 31 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
72.
Masonry Supplier’s
Statement
X
BC §27-600
RS 10-1 & 10-2
Table 10-1 fn “c”
Select if the application
proposes the installation of
structural masonry.
A supplier's statement is required to
ensure that masonry delivered to the
job site meets quality standards and
is in compliance with requirements
of the A.S.T.M.
Submit a 10J form
73.
Mechanical (MH)
Signoff
X
BC § 27-157
BC § 27-162
Select this item if the NB or
Alt 1 application has a
mechanical (MH)
application that is filed
under a separate
job
number.
If filed separately from the main
application, a signed off mechanical
(MH) application is required to
ensure that mechanical work was
completed properly.
File MH application.
Identify on the main application’s
drawings the scope of work to be
filed under the related MH
application.
On the PW-1 for the MH
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain MH application signoff or
provide letter of completion.
74.
Microfilm:
Additional Required
X
APPN 3/92
APPN 3/00
Select for all applications
where the initial filing fee is
not sufficient to cover the
cost.
A payment for final microfilming is
required if the initial filing fee is not
sufficient to cover the cost.
Pay final microfilm fee at Cashier.
Submit receipt to CO unit.
75.
Microfilm: Initial
X
BC §27-157
OPPN 2/92 & 3/79
APPN 3/92 & 3/00
This item will automatically
apply to all applications
except subdivisions.
All job filings are required to be
microfilmed.
Submit application that has been
stamped “Microfilm approved for
permit.”
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 32 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
76.
PC Filing:
Applicant/Owner
Statements*
X
This item will automatically
apply to all PC-filed
applications.
When an application is PC filed,
certain documentation must
accompany the electronic
submission to ensure that applicant
and owner agree to PC filing terms.
Submit Statement and Signature
page signed and sealed by
Applicant.
Submit Owner's Statement signed
by Owner.
77.
Place of Assembly
(PA) Signoff
X
OPPN 4/89
TPPN 20/88
BC §27-522
Select this item if the
application involves a Place
of Assembly (PA) job.
If Place of Assembly exists on the
application, the (PA) job must be
signed off to ensure safe egress
when a space is built to
accommodate assembly of 75
people or more. Requirement must
be clearly indicated in plan and at
building.
File PA application for new or
modified interior/exterior layout.
On the PW-1 for the PA
application, identify the job number
of the related NB/Alt 1 in Sec. 6.
Obtain PA application signoff or
provide letter of completion.
78.
Plumbing (PL)
Signoff
X
RS 16-4 & 16-5 Select this item if the NB or
Alt 1 application has a
plumbing (PL) application
that is filed under a
separate
job number.
If filed separately from the main
application, the Plumbing (PL
application must be signed off to
ensure that plumbing fixtures were
installed properly.
File PL application.
Identify on the main application’s
drawings the scope of work to be
filed under the related PL
application.
On the PW-1 for the PL application,
identify the job number of the
related NB/Alt 1 in Sec. 16 or Part
A of Sec. 7.
Obtain PL application signoff or
provide letter of completion.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 33 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
79.
Restriction: Deed*
X
Select if a restriction exists
on the deed to the property.
Certain deed restrictions limit the
use of the property and must be
properly noted.
Submit copy of recorded deed.
80.
Restriction:
Easement
Agreement*
X
NYC Charter
§643, §645
LPPN 1/05, 1/04 &
1/92
TPPN 10/87
Select if an easement
agreement is required to
comply with Code.
When the restriction affects
more than one parcel
owned by different parties,
the agreement must be in
the form of an easement.
Proposed work or development
could be prohibited because of BC
requirements. DOB may accept
proof of an easement agreement
that provides for alternate means of
compliance.
DOB has approved the following
easement agreements for such use:
Caretaker’s
Apartment
Lotline
Window
Driveway Off-Site
Parking
Egress Party Wall
Flood Zone Light and Air
Plumbing
System
Student
Dormitory
Submit proof of recordation of the
appropriate easement agreement
document and
Submit to DOB all proposed
easement agreements for plan
examination review. For
professionally certified applications,
professional must certify the
easement agreement is the
appropriate format and satisfies all
statutory requirements. Otherwise
the professional must request
review by the General Counsel’s
Office and
Approved easement agreement
must be signed by the fee owner,
acknowledged and recorded with
the County Register against all
affected tax lots and applicant must
submit proof of recording.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 34 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
81.
Restriction:
Restrictive
Declaration
X
LPPN 1/05 & 1/04
TPPN 10/87
Select if a restrictive
declaration is required to
comply with Code or
Zoning Resolution.
When the restriction affects
a single parcel owned by
one party, the agreement
must be in the form of a
Restrictive Declaration.
Proposed work or development
could be prohibited because of BC
requirements. DOB may accept
proof of a restrictive declaration that
provides for alternate means of
compliance.
DOB has approved the following
restrictive declaration documents:
Caretaker’s
Apartment
Lotline
Window
Driveway Off-Site
Parking
Egress Party Wall
Flood Zone Light and Air
Plumbing
System
Student
Dormitory
Submit proof of recordation of the
appropriate restrictive declaration
document and
Submit to DOB all proposed
restrictive declarations for plan
examination review. For
professionally certified applications,
professional must certify the
restrictive declaration is the
appropriate format and satisfies all
statutory requirements. Otherwise
the professional must request
review by the General Counsel’s
Office and
Approved restrictive declaration
must be signed by the fee owner,
acknowledged and recorded with
the County Register against all
affected tax lots and applicant must
submit proof of recording.
82.
Scaffold Permit
X
BC §27-1022 Select this item if a scaffold
is required to perform the
work.
If a scaffold is required, the scaffold
permit must be issued before the
permit for the main job is issued.
Obtain permit.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 35 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
83.
Self-certify
Objections*
X
TPPN 7/94 Select if applicant elects to
self-certify objections.
Applicants may elect to self-certify
objections for Dir. 14/75 filings and
Dir. 2/75 filings for 1-, 2- and 3-
family dwellings. Election must be
made prior to initial plan exam.
Prior to initial plan exam, include
election statement on PW-1 §16.
In response to objections, submit
Form AI-1.
Submit Owner’s Statement.
84.
Septic Installation:
DEP Approval
X
NYC Health Code
Sec. 143.09
NYC DEP Interim
Proc.
Select if the proposed work
involves installation of a
septic system.
Approval from the Department of
Environmental Protection (DEP) is
required to ensure that soil
percolation and absorption meets
standards to prevent groundwater
contamination.
Contact DEP for a soil suitability
inspection.
Obtain DEP permit.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 36 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
85.
Sewer Connection:
DEP SD-1 & SD-2*
X
BC §27-901
OPPN 22/88
Memo 10/24/86
Letter 12/17/86 &
9/22/89
This item will automatically
apply to all NB applications.
Select for Alt 1 or Alt 2
applications where
proposed work involves
more than 50% horizontal
enlargement.
Approval from (DEP) is required to
ensure that the property is properly
connected to storm, sanitary, or
combined sewer systems.
The SD-1 and SD-2 form is required
for any 1, 2, or 3-family home.
Submit SD-1 and -2 form and Site
Connection Proposal (SCP) Forms
certified by DEP if job is a 1, 2, or
3-family home.
86.
Sidewalk Shed
Permit
X
BC §27-1021 Select this item is a
sidewalk shed is required
to perform the work
If a sidewalk shed is required, the
shed permit must be issued before
the permit for the main job is issued.
Obtain permit.
87.
Site Connection:
DEP*
X
BC §27-901 Select this item for all
applications not subject to
the SD-1 & SD-2
requirement.
Approval from (DEP) is required to
ensure that the property is properly
connected to storm, sanitary, or
combined sewer systems.
The Site Connection form is required
for any job that is not a 1, 2, or 3-
family home.
Submit Site Connection form and
Site Connection Proposal (SCP)
Forms certified by DEP if job is not
a 1, 2, or 3-family home.
88.
Site Safety Plan
X
Memo 9/9/83
OPPN 11/87,
6/88, 15/91
BC §27-1025
Select for any application
involving a “major building"
15 or more stories, 200 ft or
more in height or 100,000
sq. ft. or more of lot
coverage, regardless of
height, unless excluded per
OPPN 6/88.
A site safety plan is required for
“major buildings” to ensure that
construction activity is conducted in
a safe manner.
Check the Site Safety box in
Section 7 of PW-1.
Provide a site safety manager until
the site is secure.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 37 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
89.
Sprinkler (SP)
Signoff
X
BC § 27-967
BC § 27-951
Select this item if the NB or
Alt 1 application has a
sprinkler (SP) application
that is filed under a
separate
job number.
If filed separately from the main
application, the sprinkler (SP)
application must be signed off to
ensure that sprinklers were installed
properly for fire protection.
File SP application.
On the PW-1 for the SP
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain SP application signoff and
provide letter of completion.
90.
Sprinkler/Standpipe
Electrical Letter
X
BC § 27-957
RS 17-9
Select this item for
plumbing work where
electricians are installing or
repairing flow and tamper
switches.
A sprinkler/standpipe electrical letter
is required to ensure all flow and
tamper switches are wired to code
and functioning properly.
Electrician must provide a signed
and sealed letter on letterhead
certifying all flow and tamper
switches are wired to code and
functioning properly.
91.
Standpipe (SD)
Signoff
X
BC § 27-967
BC § 27-951
Select this item if the NB or
Alt1 application has a
standpipe (SD) application
that is filed under a
separate
job number.
If filed separately from the main
application, the standpipe (SD)
application must be signed off to
ensure that a standpipe system was
installed properly for fire protection.
File SD application.
On the PW-1 for the SD
application, identify the job number
of the related NB/Alt 1 in Sec. 16 or
Part A of Sec. 7.
Obtain SD application signoff or
provide letter of completion.
92.
Steel Affidavit:
Preliminary*
X
BC §27-614(a)
Memo 7/15/74
Table 10-1 fn “c”
Select for any application
that uses structural steel.
A preliminary steel affidavit is
required to ensure that structural
steel proposed for use meets quality
standards.
Submit B Form 20SS.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 38 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
93.
Steel Affidavit:
Final*
X
BC §27-614(a)
Memo 7/15/74
Table 10-1 fn “c”
Select for any application
that proposes the use of
structural steel.
A final steel affidavit is required to
ensure that structural steel used for
the job meets quality standards.
Submit B Form 24SS.
94.
Street: New Name
Approved*
X
GCL §35 & 36
Memo: 4/1/83
Select if the application
results in a new street.
Each new street must be accurately
recorded in City records.
Obtain street name verification
stamp on back of PW-1 from
Topographic Unit of Borough
President's Office. Submit stamp
with PW-1.
95.
Street: Unmapped -
Notify Emergency
Agencies*
X
GCL §36
OPPN 7/97
Select if work involves
zoning lots fronting on new
private streets.
Notice of a new private street and/or
house number to City emergency
service units (FDNY, NYPD and
Dept of City Planning) is necessary
to insure effective emergency
response.
Submit copies of affidavit (ER1 or
ER2) to FDNY, NYPD and
Department of City Planning.
96.
Street Tree
Checklist
X
ZR §23-03 Automatically applies to all
NB, A1 and A2
enlargement applications.
Applicant must certify the number of
street trees required determined by
property street frontage as per the
Zoning Resolution. The applicant
must certify number of existing tress,
number of trees to be removed and
number of trees to be planted to
satisfy tree planting requirements
on-site or off-site. In certain
circumstances, this requirement may
be satisfied by payments to the DPR
tree fund.
Submit Street Tree Checklist (DOB
form ST-1)
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 39 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
97.
Street Tree Sign-Off
X
ZR §23-03
Automatically applies to all
NB, A1 and A2
enlargement applications.
To ensure that the proposed number
of trees was planted properly or
payment into tree fund was made,
DOB requires sign-off
documentation from the Parks
Department.
Submit signed-off tree planting
permit from DPR, and/or
tree fund payment receipt from
DPR, and/or
30-day off-site location request
waiver from DPR
Depending on planting
requirements, applicant may have
to submit more than one for the
aforementioned documents from
DPR
98.
Subdivision Signoff*
X
Select this item if the NB is
for a property with an
existing structure that will
not be demolished.
If the property is being subdivided,
the subdivision must be approved
before the main job can be
approved.
File SI application.
Obtain SI application signoff.
99.
Survey: Initial
X
BC §27-157(a)(1) Select for all NB and
Alterations involving an
increase in floor area or
foundations.
A lot diagram drawn in accordance
with an accurate boundary survey of
the site, made by a licensed
surveyor, is required to verify
existing construction.
Submit a site survey by a licensed
surveyor with your filing.
The boundary survey must be
attached to and form part of the lot
diagram
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 40 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
100.
Survey: Final
X
BC §27-219 This item will automatically
apply to NB and Alt 1
applications.
A final survey conducted by a
licensed surveyor is required to
ensure that all construction, street
improvements, and related work on
the site were completed per
approved plans.
Submit final survey sealed by
surveyor and signed by PE/RA of
record.
Swimming Pool:
DEP Approval
101.
Swimming Pool:
DOH Approval
X
BC § 27-488
BC § 27-915
RCNY 165.01 &
165.03
Select if installing a
swimming pool.
A DEP permit is required for pools
above ground more than 500 sq. ft.
and for in ground more than 400 sq.
ft. All pools must have an indirect
connection for wastewater or an
acceptable pH discharge.
A DOH permit is required for pools
that will accommodate more than
one household (i.e. public access
pools and/or shared facilities.)
Obtain a Letter of No Objection
from DEP.
Obtain a Permit or No Objection
from DOH.
102.
Tax lot: Tentative
Lot Number Issued*
X
AC §11-203(b)
Memo 2/9/81
OPPN 30/92
Select for all SI
(Subdivision Improved) and
any NB or Alt 1 applications
that will result in new tax lot
numbers.
If proposed work involves
subdivision or merger of lots,
tentative lot numbers are required to
be assigned before the Dept of
Finance (DOF) establishes final tax
lots.
Submit DOF Form RP 604
indicating tentative lot numbers
approved and signed by DOF’s
Real Property Assessment Bureau
Surveying Division. Form must also
be signed and sealed by PE/RA.
103.
Tax lot: Final Lot
Number Issued
X
AC§11-203(b)
LL 7/81, 8/81,
9/81
Memo 2/9/81,
4/16/81
This item will automatically
apply to NB and Alt 1
applications.
Certification from the Real Property
Assessment Division of the Dept of
Finance is required to ensure that
tentative tax lots have been
finalized.
Submit certified copy of tax map
from Department of Finance.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 41 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
104.
Transit Authority
Approval*
X
Memo 11/29/74
AC §26-228
1 RCNY §21(d)(4)
Select for any application
involving structural work
within 200 feet of a Transit
Authority or other railway
right-of-way.
TA approval is required when
construction or legalization work is in
close proximity to transit
infrastructure. TA maintains a list of
tagged properties.
Obtain approval or exemption letter
from railway or Transit Authority.
105.
Tree Removal:
Outside Property
Line/Parks
Approval*
X
AC §27-1030 Select if a tree located
outside the property line is
to be removed.
Removal of trees outside the
property line requires Parks
Department approval.
Obtain approval from Parks Dept.
Submit to DOB.
106.
Tree Removal:
Special Zoning
District/CPC
Approval*
X
ZR §119-111,
§105-11, §107-32
Select if a tree with
diameter more than 6
inches will be removed in a
special zoning district
(South Richmond, Natural
Area or Special Hillside
Preservation).
Removal of trees in these districts is
prohibited unless CPC approval is
obtained
Obtain approval from CPC.
Submit to DOB
107.
Urban Renewal
Area: HPD
Approval*
X
Gen. Mun. Law
§503 (h)
1 RCNY §21-01
(d)(3)
Select for NB and Alt 1 if
the application concerns a
property located in an
Urban Renewal Area.
If the property is located in an Urban
Renewal Area, approval from the
Dept of Housing and Preservation
Development (HPD) is required.
Obtain approval from HPD.
Submit to DOB.
108.
US Army Corps of
Engineers
Approval*
X
River Harbor Act
of 1899
Title 33 of Code of
Fed Regs Part
320.1 (Clean
Water Act)
Select if work requires a
permit from the US Army
Corps of Engineers.
Approval from Army Corps is
required to ensure proposed work
meets Army Corps requirements
pertinent to waterfront bulkhead
areas, wetlands, and other
designated areas (i.e. changes in
bulkhead for existing waterfront.).
File application with Army Corps of
Engineers for review letter.
Submit to DOB prior to approval.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 42 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
109.
Violations: Clear All
X
NYC Charter
645(b)(3)d
AC §26-222
MDL §301.1
This item will automatically
apply to NB and Alt 1
applications.
In order to issue a CO the building
must substantially comply with the
BC and other laws, rules, and
regulations, including that no
violations are outstanding.
Ensure that all open violations on
the property have been cleared.
110.
Water Supply
(private): DOH
Approval
X
NYC Health Code
§141.021
Select for NB, Alt 1 and
Alt 2 applications involving
new water services through
private connection or
modifications to existing
service.
Approval from the DOH for private
water supply is required to ensure
that the property has adequate
water service.
Obtain permits 33 and 37 from
DOH.
Submit to DOB.
111.
Waterfront Area
Zoning Compliance*
X
ZR §62-00
ZR §62-10
ZR §62-11
ZR §62-12
Select for any application
subject to waterfront area
zoning regulations.
Compliance with waterfront area
zoning regulations is required to
ensure that work proposed under
this application meets requirements
for special uses, bulk, parking,
loading, public access, and other
applicable regulations.
Show conformance / compliance
with ZR Article VI, Chapter 2 on
plans.
112.
Zoning Exhibit I:
Certification*
X
Memo 5/18/78
Paragraph (c) &
(e) of Zoning Lot
definition in ZR
§12-10
Select for NB jobs if the
property is in single
ownership.
Select for Alt 1 and Alt 2
jobs involving
enlargements where the
property is in single
ownership.
The Zoning Resolution requires that
a title company licensed to do
business in NY State certify the
parties having interest in the zoning
lot.
Submit to DOB.
File in connection with Exhibit III.
General Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 43 -
Required Prior to:
Item Description
Application
Approval
Permit
Signoff
References Applicability Explanation How to Satisfy
113.
Zoning Exhibit II:
Certification*
X
Memo 5/18/78
Paragraph (d)and
(f) of Zoning Lot
definition in ZR
§12-10
Select for NB jobs if the
property is in multiple
ownership.
Select for Alt 1 and Alt 2
jobs involving
enlargements where the
existing lots are in multiple
ownership.
The Zoning Resolution requires that
a title company licensed to do
business in NY State certify the
parties having interest in the zoning
lot.
Submit to DOB.
Must be filed in conjunction with
Zoning Lot Certification III and IV.
114.
Zoning Exhibit III:
Description and
Ownership
Statement*
X
Memo 5/18/78
Last paragraph of
Zoning Lot
definition in ZR
§12-10
Select for any job requiring
a Zoning Lot Certification
Exhibit I or II and for any
subdivision of improved
property.
Zoning lot description and
statement of ownership is required
to identify the zoning lot.
File with the County Clerk’s office
or City Register and obtain a CRFN
number which is the equivalent of a
reel/page number.
Submit to DOB.
115.
Zoning Exhibit IV:
Certification*
X
Memo 5/18/78
Paragraph (d) of
Zoning Lot
definition in ZR
§12-10
Select for any job requiring
a Zoning Lot Certification
Exhibit II.
The Zoning Resolution requires all
parties in interest listed in exhibit II
must sign exhibit IV or V and have
executed and recorded the
declaration or waived their
respective rights.
File with the County Clerk’s office
or City Register and obtain a CRFN
number which is the equivalent of a
reel/page number.
Submit to DOB.
116.
Zoning Exhibit V:
Certification*
X
Memo 5/18/78
Paragraph (d) of
Zoning Lot
definition in ZR
§12-10
Select for any job requiring
a Zoning Lot Certification
Exhibit II, if any parties
listed in exhibit II are
waiving interest.
The Zoning Resolution requires that
each party in interest has executed
and recorded the declaration or
waived their respective rights.
File with the County Clerk’s office
and obtain a CRFN number that is
the equivalent of a reel/page
number prior to approval of
application.
Submit to DOB.
Post-Approval Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 44 -
Post-Approval Required Items
The following Required Items may be added to a job after the initial list of Required Items for that job has been completed. These items
typically apply when an applicant is seeking a Temporary Certificate of Occupancy or if an existing Required Item that has been
satisfied is no longer valid or has expired, e.g., a final inspection signoff expires.
Proposed New Description Source Applicability Explanation How to Satisfy
117.
Escrow Letter (Attorney)
OPPN 5/92 This item will be added to an NB or Alt
1 application seeking a temporary CO
for a 1, 2 or 3-family home.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires the builder
deposit escrow to secure completion
of the work and a final CO.
Submit completed Escrow
Agent/Attorney letter certifying
that the builder has made the
required escrow deposit.
118.
Escrow Letter (Builder)
OPPN 5/92 This item will be added to an NB or Alt
1 application seeking a temporary CO.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires the builder
deposit escrow to secure completion
of the work and a final CO.
Submit original, notarized Builder
Certification form certifying that
the required escrow will be
deposited at closing
119.
Fee: TCO Payment ($100)
AC §26-214 This item will be added to an NB or Alt
1 application seeking a temporary CO.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires payment of a
fee.
Pay fee at Cashier.
Submit receipt to CO Unit.
120.
Temp Construction
Signoff
BC
§27-214 - §27-218
AC §26-222
OPPN 6/93,
16/92, 5/92
This item will be added to an NB or Alt
1 application seeking a temporary CO.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires a signoff to
ensure that construction work in
those parts of the building for which
occupancy is sought passes DOB’s
Construction inspection.
Obtain temporary Construction
signoff for floors/spaces to be
occupied from the Construction
Division.
Post-Approval Required Items Subject to change.
*Denotes item that can only be received by technical staff. - 45 -
Proposed New Description Source Applicability Explanation How to Satisfy
121.
Temp Elevator Signoff
(Hi-Rise Only)
BC §27-218 This item will be added to an NB or Alt
1 application seeking a temporary CO.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires a signoff to
ensure that elevator work in those
parts of the building for which
occupancy is sought passes DOB’s
Elevator inspection.
Obtain temporary Elevator signoff
for floors to be occupied from the
Elevator Division.
122.
Temp Plumbing Signoff -
Partial Building
BC §27-218
This item will be added to an NB or Alt
1 application seeking a temporary CO
for a portion of a building.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires a signoff to
ensure that plumbing work in areas
of the building for which occupancy
is sought passes DOB’s Plumbing
inspection.
Obtain temporary Plumbing
signoff for floors to be occupied
from the Plumbing Division.
123.
Temp Plumbing Signoff -
Entire Building
BC §27-218 This item will be added to an NB or Alt
1 application seeking a temporary CO
for an entire building.
When an applicant seeks a
temporary Certificate of Occupancy
(CO), DOB requires a signoff to
ensure that plumbing work in the
building in which occupancy is
sought passes DOB’s Plumbing
inspection.
Obtain temporary Plumbing
signoff for building occupancy
from the Plumbing Division.
124.
Update Final
Construction Signoff
BC §27-210 This item will be added to an NB or Alt
1 application if the Final Construction
Signoff was satisfied more than (1)
year prior or 18 months for residential.
DOB requires an updated
construction signoff to ensure
construction work passes DOB's
construction inspection.
Obtain an updated final
construction signoff from the
Construction Division.
- 46 -
Helpful Information
Abbreviation Key:
AC
Administrative Code
APPN
Administrative Policy and
Procedure Notice
BC
Building Code
BIS
Building Information System
BSA
Board of Standards and
Appeals
CPC
City Planning Commission
Dir
Building Department Directive
DEP
Department of Environmental
Protection
DOB
Department of Buildings
DOH
Department of Health
DOT
Department of Transportation
FDNY
Fire Department of City of New
York
HPD
Department of Housing,
Preservation and Development
Letter
Building Department
Letter/Memorandum
LL
Local Law
LPPN
Legal Policy and Procedure
Notice
MDL
Multiple Dwelling Law
Memo
Building Department
Memorandum
NYC Charter
Charter of the City of New
York
NYC DEP
NYC Department of
Environmental Protection
NYCRR
NY State Codes, Rules, and
Regulations
NYS DOH
NY State Department of
Health
NYS ECL
New York State Environmental
Conservation Law
OPPN
Operations Policy and
Procedure Notice
P.E.
Professional Engineer
R.A.
Registered Architect
RCNY
Rules of the City of New York
RS
Reference Standard
TPPN
Technical Policy and
Procedure Notice
ZR
Zoning Resolution
Application Types:
NB: New Building
Alt 1:
A major alteration in which the
use, occupancy or egress of an
existing building changes.
Alt 2:
An alteration where the use,
occupancy or egress of a building
does not change, but has multiple
work types.
Alt 3:
A minor alteration that involves
only one work type.
DM
Demolition and Removal
PA Public Assembly
(Place of Assembly)
SG
Sign
SI
Subdivision
Permit/Work Type Key:
AL
Alteration
BL
Boiler
CC
Curb Cut
CH
Chute
EA
Earthwork
EQ
Construction Equipment
EW
Equipment Work
FA
Fire Alarm
FB
Fuel Burning
FN
Fence
FO
Foundation/Earthwork
FP
Fire Suppression
FS
Fuel Storage
MH
Mechanical/HVAC
NB
New Building
OT
Other
PL
Plumbing
SD
Standpipe
SF
Scaffold
SH
Sidewalk Shed
SP
Sprinkler
- 47 -
Required Item Comparison Chart
The name/description of many Required Items has changed. The meaning remains the same. Refer
to this chart to identify the new name/description of an existing Required Item.
Old Item Name:
New Item Name:
1. $100 Fee for Temp C.O Fee: TCO Payment ($100)
2. Adult Est. – Check with Chief Engineer Adult Establishment Approval
3. Applicant to Self-certify Objections Self-certify Objections
4. Asbestos ASB 4 Asbestos ACP 7 or 5 or ASB 4
5. Asbestos – ACP 5 or 7 Asbestos ACP 7 or 5 or ASB 4
6. Boiler (BL) Application Required Boiler (BL) Signoff
7. Borough Commissioner Waiver of
Local Law 58 of 1987
Local Law 58 of 1987 Waiver
8. BSA/CPC Variance BSA Variance
BSA/CPC Approval
9. Builders Attorney (Escrow Letter) Escrow Letter (Attorney)
10. Builders Letter (Escrow Letter) Escrow Letter (Builder)
11. Certification of Smoke Detectors Install Detector: Smoke
12. Compliance Required – Waterfront Zoning Waterfront Area Zoning Compliance
13. Construction (OT) Application Required Construction (OT) Signoff
14. Cost Affidavit Cost Affidavit: Estimated
15. Curb Cut # Required Curb Cut: Provide Existing Number
16. Curb Cut (CC) Application Curb Cut (CC) Signoff
17. Deed Restriction Restriction: Deed
18. Deferred Fees Fee: Pay Deferred Fees
19. Demolition Signoff Prior to CO Signoff Demolition (DM) Job Signoff
20. DEP: SD-1, SD-2 Sewer Connection: DEP SD-1 & SD-2
21. Disability insurance Insurance: Disability
22. DOF – RP604 Form (P/E signed & approved); Tax lot: Tentative Lot Number Issued
23. DOH – Priv Water Supply/Swim Pool/Tree Rmvl” Water Supply (private): DOH Approval
Swimming Pool: DEP Approval
Tree Removal: Special Zoning District/CPC Approval
Tree Removal: Outside Property Line/Parks Approval
24. Easement (C of O time) Restriction: Easement Agreement
25. Electrical Signoff Final Electrical Signoff
26. Elevator Application Elevator Job Signoff
27. Fee Adjustment (Scope of Work Changed) Fee: Adjustment (Scope of Work Changed)
28. Final Cost Affidavit Cost Affidavit: Actual
29. Final Survey Survey: Final
30. Fire Alarm Application – FD Approval Fire Alarm/Signal System (FA) Signoff
31. Fire Suppression (FP) Application Fire Suppression System (FP) Signoff
32. Fire - FP Plan Approval by Fire Dept Fire Protection Plan (FPP): FDNY Approval
33. Five Day Notice of Excavation Excavation or Demolition: 5-Day Notice
34. Flood Zone Flood Zone: FEMA Elevation Certificate
35. Foundation Plans Required Foundation Plan Approval
Foundation Signoff
36. Fuel Burning (FB) Application Required Fuel Burning (FB) Signoff
- 48 -
Old Item Name: New Item Name:
37. Fuel Storage (FS) Application Required Fuel Storage (FS) Signoff
38. Gasoline Tank Application Gasoline Tank Signoff
39. HPD Approval – Urban Renewal Area Urban Renewal Area: HPD Approval
40. HPD: Clinton District Certification Clinton District: HPD Certification
41. Highway Letter BPP: Final Signoff
42. House Number Verification by Borough President Address: New House Number Approved
43. In Conjunction with Job _____ (Note # in
Comments)
Identify the Primary Job (PW1 §16)
44. Legalization: Pay Express Cashier Fee: Civil Penalty for Legalization
45. Liability Insurance Insurance: Liability
46. Little E – DEP Final Notice of Satisfaction Environmental “E” - DEP Notice of Satisfaction
47. Little E – DEP Notice to Proceed Environmental “E” - DEP Notice to Proceed
48. Loft Board Approval Loft Board Certificate
49. Marquee Permit Marquee (OT) Signoff
50. Mechanical (MH) application/plans Mechanical (MH) Signoff
51. Microfilm Required Microfilm: Initial
52. NYS Dept of Environmental Protection Backflow Preventer
(RPZ or Double-Check Valve Assembly)
53. Open Applications Search Applications: Signoff Open Jobs
54. Open Violations Search Violations: Clear All
55. PA Application & Signoff; Place of Assembly (PA) Signoff
56. Plumbing (PL) Application Required Plumbing (PL) Signoff
57. Preliminary Steel Affidavit Steel Affidavit: Preliminary
Steel Affidavit: Final
58. Re-microfilming Necessary Microfilm: Additional Required
59. Site Suitability for Septic by DEP Septic Installation: DEP Approval
60. Site Survey Survey: Initial
61. Special Clinton District Certification Clinton District: HPD Certification
62. Sprinkler (SP) Application Sprinkler (SP) Signoff
63. Standpipe (SD) Application Standpipe (SD) Signoff
64. State Dept – No Objection Let. Foreign Prop Foreign Government Property: State Department Letter
65. Street Status Verification by Boro Pres Street: New Name Approved
66. Subdivision Approval Before Job Approval Subdivision Signoff
67. TA Approval Transit Authority Approval
68. Tax Lot Certified – RPAD (DOF)
Tax Lot: Tentative Lot Number Issued
Tax Lot: Final Lot Number Issued
69. Temp Const. Signoff Temp Construction Signoff
70. Temp Elev COFO Signoff (Hi-Rise Only) Temp Elevator Signoff (Hi-Rise Only)
71. Temp Plumbing Signoff (Hi-Rise Only) Temp Plumbing Signoff – Partial Building
Temp Plumbing Signoff- Entire Building
72. Unmapped Street: Notified Emergency Agencies; Street: Unmapped - Notify Emergency Agencies
73. Verify Address Address: New House Number Approved
74. Verify Tax Lot Tax Lot: Final Lot Number Issued
75. Waiver/Affidavit of Workers Comp Insurance: Workers’ Comp. Waiver/Affidavit
76. Workers’ Compensation Insurance: Workers’ Compensation
77. Zoning Declaration I Zoning Exhibits I, II, IV or V: Certifications
Zoning Exhibit III: Description and Ownership
Statement
- 49 -
Required Items Sorted by “When Required”
The following chart is sorted based upon when a Required Item must be submitted prior to.
Application Approval: Permit: Signoff:
1. Address: New House Number
Approved
1. Clinton District: CPC Special
Permit
1. Applications: Signoff Open Jobs
2. Adult Activity Approval 2. Cost Affidavit: Estimated 2. Backflow Preventer
3. Adult Establishment Approval 3. CPC: Hudson Yards Final
Certification
3. Boiler (BL) Signoff
4. Anti-Harassment Area
Checklist
4. Demolition Application 4. Certificate of Occupancy
5. Asbestos ACP 7 or 5 or ASB 4 5. Dir. 14 ID of Responsibility 5. Clinton District: HPD Cure
Certification
6. BSA or CPC Approval 6. Equipment (EQ) Permits 6. Construction (OT) Signoff
7. BSA Variance 7. Excavation or Demolition: 5-Day
Notice
7. Cost Affidavit: Actual
8. BPP: Design Commission
Approval - Distinctive Sidewalk
8. HPD: Inclusionary Housing
Letter
8. Curb cut (CC) Signoff
9. Clinton District: HPD
Certification
9. Insurance: Disability 9. Demolition Job Signoff
10. Clinton District: Restrictive
Declaration
10. Insurance: Liability 10. Detector: Carbon Monoxide
11. CPC: Hudson Yards Initial
Certification
11. Insurance: Workers’ Comp.
Waiver/Affidavit
11. Detector: Smoke
12. Curb Cut: Provide Existing
Number
12. Insurance: Workers’
Compensation
12. Elevator Job Signoff
13. Design Commission Approval:
City-owned property
13. Masonry Manufacturer’s
Statement
13. Environmental “E” - DEP Notice
of Satisfaction
14. Environmental “E” - DEP Notice
to Proceed
14. Microfilm: Initial 14. Equipment Use (EUP) Permits
15. Fee: Adjustment (Scope of
Work Changed)
15. Scaffold Permit 15. Fee: Pay Deferred Fees
16. Fee: Civil Penalty for
Legalization
16. Sidewalk Shed Permit 16. Final Construction Signoff
17. Fire Alarm (FA): FDNY Approval 17. Site Safety Plan 17. Final Electric Signoff
18. Foreign Government Property:
State Department Letter
18. Final Elevator Signoff
19. Foundation Plan Approval 19. Final Plumbing Signoff
20. HPD: Certificate of No
Harassment
20. Final Sewer House Connection
Signoff
21. Identify the Primary Job
(PW1 §16)
21. Fire Alarm/Signal System (FA)
Signoff
22. Landmarks Approval 22. Fire Protection Plan (FPP):
FDNY Approval
23. Local Law 58 of 1987 Waiver 23. Fire Retardant Treated Wood:
FDNY Certificate
- 50 -
Application Approval: Permit: Signoff:
24. Loft Board Certificate 24. Fire Suppression System (FP)
Signoff
25. PC Filing: Applicant/Owner
Statements
25. Flood Zone: FEMA Elevation
Certificate
26. Restriction: Deed 26. Folder Review
27. Restriction: Easement
Agreement
27. Foundation Signoff
28. Restriction: Restrictive
Declaration
28. Fuel Burning (FB) Signoff
29. Self-certify Objections 29. Fuel Storage (FS) Signoff
30. Sewer Connection: DEP SD-1 &
SD-2
30. Gasoline Tank Signoff
31. Site Connection: DEP 31. HPD: Inclusionary Housing
Eligibility Certificate
32. Steel Affidavit: Preliminary 32. Landmarks Signoff
33. Street: New Name Approved 33. Marquee (OT) Signoff
34. Street: Unmapped - Notify
Emergency Agencies
34. Masonry Supplier’s Statement
35. Street Tree Checklist 35. Mechanical (MH) Signoff
36. Subdivision Signoff 36. Microfilm: Additional Required
37. Survey: Initial 37. Place of Assembly (PA) Signoff
38. Tax lot: Tentative Lot Number
Issued
38. Plumbing (PL) Signoff
39. Transit Authority Approval 39. Septic Installation: DEP
Approval
40. Tree Removal: Outside
Property Line/Parks Approval
40. Sprinkler (SP) Signoff
41. Tree Removal: Special Zoning
District/CPC Approval
41. Sprinkler/Standpipe Electrical
Letter
42. Urban Renewal Area: HPD
Approval
42. Standpipe (SD) Signoff
43. US Army Corps of Engineers
Approval
43. Steel Affidavit: Final
44. Waterfront Area Zoning
Compliance
44. Street Tree Sign-Off
45. Zoning Exhibits I, II, III, IV and V 45. Survey: Final
46. Swimming Pool: DEP Approval
47. Tax lot: Final Lot Number
Issued
48. Violations: Clear All
- 51 -
Application Approval: Permit: Signoff:
49. Water Supply (private): DOH
Approval
- 52 -
Index
Adult Establishment ...............................7, 9, 45, 47
Alteration Type 1 (Alt 1) .. 3, 9, 11-13, 15-25, 27-31,
34-36, 38-44
Alteration Type 2 (Alt 2) .........11, 15, 17-18, 20, 23,
27-28, 34, 40-41, 44
Alteration Type 3 (Alt 3) ...11, 15, 17-18, 23, 27-28,
44
Asbestos............................................... 7, 11, 45, 47
Board of Standards and Appeals (BSA) ....7, 12-13,
44-45, 47
Boiler ........................................7, 12, 24, 44, 45, 47
Builders Pavement Plan (BPP) ..........2, 7, 9, 12, 49
Buildings Information System (BIS) ....1, 3-6, 16-17,
27-28, 44
Certificate of Occupancy (CO) ...... 9, 13, 20-21, 23,
30, 40, 42-43, 45
City Planning Commission (CPC)....7, 8, 13-16, 39,
44-45, 47-48
Clinton District..................................7, 13-14, 46-47
Construction………3, 7, 8, 15, 18-20, 23, 29, 42-48
Cost......................................................7, 15, 45, 47
Curb Cut....................................7, 16, 18, 44-45, 47
Deed.....................................................8, 31, 45, 48
Demolition .................................7, 17, 19, 44-45, 47
Dept. of Finance (DOF).............................38, 45-46
Dept. of Housing Preservation And Development
(HPD)................ 7, 8, 13-14, 24-25, 39, 44, 46-48
Dept. of Transportation (DOT) ............................. 44
Design Commission .............................7, 10, 12, 49
Detector (Smoke/Carbon Monoxide) ...7, 17, 45, 47
Directive 14 ....................................7, 18, 21, 34, 47
Disability............................................... 7, 25, 45, 47
Electrical................................7, 8, 20, 36, 45, 47-48
Elevator ..................................7, 8, 18, 20, 43, 4547
Environmental ...............7, 11, 18, 24, 34, 44, 46-47
Equipment .......................................7, 18-19, 44, 47
Excavation............................................7, 19, 45, 47
FDNY / Fire Safety... 7, 21-22, 24, 37, 44-45, 47-48
Fee .........................................7, 8, 19-20, 42, 45-47
FEMA ...................................................7, 23, 45, 48
Fence ................................................................... 44
Flood .................................................................... 23
Folder ...................................................................23
Foundation ................................7, 23, 44, 45, 47-48
Fuel..................................................7, 24, 44-46, 48
Gasoline ...............................................7, 24, 46, 48
Hudson Yards........................................7, 15-16, 47
Insurance......................................... 7, 25-26, 45-47
Landmarks....................................... 7, 27-28, 47-48
Loft Board..............................................7, 28, 46-47
Marquee ................................................7, 29, 46-48
Masonry.................................................7, 29, 47-48
Mechanical ...............................7, 18, 30, 44, 46, 48
Microfilm...............................................................30
New Building ........3, 9-13, 15-18, 20-25, 27, 29-31,
34-44
Occupancy ...............................7, 13, 23, 42, 43, 47
Penalty...................................................7, 19, 46-47
Place of Assembly (PA)..................8, 31, 44, 46, 48
Plumbing ..........7-8, 11, 20-21, 31-33, 43-44, 46-48
Post Approval Amendment (PAA)........................19
Safety .........................................................8, 35, 47
Scaffold.................................................8, 33, 44, 47
Septic....................................................8, 34, 46, 48
Sewer ....................................7, 8, 21, 34, 45, 47-48
Sign ......................................................................44
Site Survey................................ 8, 37-38, 45-46, 48
Sprinkler ....................................8, 35-36, 44, 46, 48
Standpipe .......................................8, 36, 44, 46, 48
Street.....................................................8, 37, 46-48
Subdivision................................8, 37-38, 44, 46, 48
Swimming Pool.....................................8, 38, 45, 48
Tax...................................................8, 38, 45-46, 48
Temporary Certificate of Occupancy (TCO)....8, 42,
45
Transit...................................................8, 39, 46, 48
Tree.................................................8, 38-39, 45, 48
Variance ...............................................................12
Violation................................................8, 40, 46, 48
Water........................................................11, 22, 40
Waterfront.............................................8, 40, 45, 48
Zoning... 2, 7-9, 12, 18, 23, 25, 32-33, 39-41, 44-46,
48