What the indicators measure
Procedures to obtain an electricity connection (number)
Submitting all relevant documents and obtaining all necessary
clearances and permits
•
Completing all required notifications and receiving all necessary
inspections
•
Obtaining external installation works and possibly purchasing
material for these works
•
Concluding any necessary supply contract and obtaining final
supply
•
Time required to complete each procedure (calendar days)
Is at least 1 calendar day
•
Each procedure starts on a separate day
•
Does not include time spent gathering information
•
Reflects the time spent in practice, with little follow-up and no
prior contact with officials
•
Cost required to complete each procedure (% of income per
capita)
Official costs only, no bribes
•
Value added tax excluded
•
The reliability of supply and transparency of tariffs index (0-8)
Duration and frequency of power outages (0–3)
•
Tools to monitor power outages (0–1)
•
Tools to restore power supply (0–1)
•
Regulatory monitoring of utilities’ performance (0–1)
•
Financial deterrents limiting outages (0–1)
•
Transparency and accessibility of tariffs (0–1)
•
Price of electricity (cents per kilowatt-hour)*
Price based on monthly bill for commercial warehouse in case
study
•
*Note:
measures the price of electricity, but it is
not included in the ease of doing business score nor in the ranking
on the ease of getting electricity.
Doing Business
Case study assumptions
To make the data comparable across economies, several assumptions about the warehouse, the
electricity connection and the monthly consumption are used.
The warehouse:
- Is owned by a local entrepreneur and is used for storage of goods.
- Is located in the economy’s largest business city. For 11 economies the data are also collected for
the second largest business city.
- Is located in an area where similar warehouses are typically located and is in an area with no
physical constraints. For example, the property is not near a railway.
- Is a new construction and is being connected to electricity for the first time.
- Has two stories with a total surface area of approximately 1,300.6 square meters (14,000 square
feet). The plot of land on which it is built is 929 square meters (10,000 square feet).
The electricity connection:
- Is a permanent one with a three-phase, four-wire Y connection with a subscribed capacity of 140-
kilo-volt-ampere (kVA) with a power factor of 1, when 1 kVA = 1 kilowatt (kW).
- Has a length of 150 meters. The connection is to either the low- or medium-voltage distribution
network and is either overhead or underground, whichever is more common in the area where the
warehouse is located and requires works that involve the crossing of a 10-meter road (such as by
excavation or overhead lines) but are all carried out on public land. There is no crossing of other
owners’ private property because the warehouse has access to a road.
- Does not require work to install the internal wiring of the warehouse. This has already been
completed up to and including the customer’s service panel or switchboard and the meter base.
The monthly consumption:
- It is assumed that the warehouse operates 30 days a month from 9:00 a.m. to 5:00 p.m. (8 hours
a day), with equipment utilized at 80% of capacity on average and that there are no electricity cuts
(assumed for simplicity reasons) and the monthly energy consumption is 26,880 kilowatt-hours
(kWh); hourly consumption is 112 kWh.
- If multiple electricity suppliers exist, the warehouse is served by the cheapest supplier.
- Tariffs effective in January of the current year are used for calculation of the price of electricity for
the warehouse. Although January has 31 days, for calculation purposes only 30 days are used.