Grid Development Plan Electricity 2037 / 2045, Version 2023, second draft 5
GDP compact
The scope and cost volume of the expansion grid will
therefore increase significantly compared to the previ-
ous GDP. Compared to the project portfolio proposed in
the GDP 2035 (2021), the present GDP 2037 / 2045 (2023)
identifies new onshore projects with a route length of
5,620 km and additional investments of EUR 52.3 billion.
This is particularly attributable to the designation of five
additional DC projects, which are necessary to secure
the required transport task and are not yet included
in the current Federal Demand Plan (BBP). Bundling
options with each other or with existing DC projects are
mostly possible or are being examined. The new DC
projects increase the north-south as well as the east-west
transport capacity. Other key drivers for the additional grid
development measures are the strong expansion of re-
newable energy in the north, the dismantling of conven-
tional power plants, the interconnected energy exchange
with foreign countries, and the increasing loads in the
course of achieving climate neutrality in all sectors.
Regarding to the results of the grid development target
grids for the years 2037 and 2045 are almost identical.
This is mainly due to the fact that onshore expansion of
renewable energy between 2037 and 2045 is almost com-
pleted. The moderate increase in onshore renewable en-
ergy capacities by 2045 may cause additional bottlenecks
in the onshore grid. However, it can be offset by the grid
structures in place at that time and correspondingly flex-
ible demand, especially from electrolysers, centralised
and decentralised battery storage as well as demand
side management. A majority of the carbon-neutral grid
must therefore already be implemented in 2037.
Considering these assumptions, the target grid consists
of a robust portfolio of grid enhancement and expansion
measures that are necessary for all scenarios. All projects
presented in GDP 2037 / 2045 (2023) should therefore be
considered to be ‘no-regret’. In the scenarios, the desig-
nated target grid only differs in terms of the remaining
redispatch demand. Currently, there are still high uncer-
tainties due to the not yet fully completed legal planning
for the expansion of renewable energy (including at the
federal states level), the decarbonisation strategies of the
industry or the planning for the future hydrogen economy.
It is important to clarified in the following GDP cycles to
which extent the remaining redispatch can be further
reduced, and especially whether it requires additional
moderate grid expansion or other technical measures.
The onshore initial grid comprises AC and DC measures
totalling around 6,950 km with an estimated investment
volume of EUR 50 billion. For the onshore grid expansion,
grid enhancements AC amount to 6,125 km. Furthermore,
there are about 180 km of DC enhancement measures.
Another 1,714 km are accounted for new AC construction
measures and 4,396 km new DC construction measures.
In total, the onshore expansion grid for all scenarios
includes 12,413 km. For scenarios A / B / C 2037, the in-
vestment costs amount to around EUR 106.1 billion. The
investment costs for the onshore expansion grid of the
A / B / C 2045 scenarios are EUR 0.1 billion higher.
The system stability analyses show considerable addi-
tional demand for reactive power compensation as well
as for the control of grid disconnections in the form of
instantaneous reserve, which already occur in the an-
alysed intermediate scenario 2030. As a consequence,
previously reported plants must be prioritised and made
available via grid-supporting contributions from third
parties (e.g. provision from the distribution grids, from
large consumers such as electrolysers, and other sys-
tem participants, possibly through market procurement).
The analyse on transient stability indicates that control-
lability could no longer be safely guaranteed in individual
hours after conceptual fault clearance in case of distur-
bances. Therefore, in order to maintain system stability,
additional solution concepts must be developed beyond
the suggested measures. The results are presented in
the accompanying document of the stability analyses, and
the necessary measures are indicated.
Compared to the first draft of the GDP 2037 / 2045 (2023),
the investment costs in the second draft of the GDP have
increased by EUR 12.5 billion. This is mainly attributable
to the consideration of additional projects based on addi-
tional demand for transformers and substations between
the distribution and transmission grid. Other contribut-
ing factors include an update of the scope and costs of
existing projects as well as the updated requirements
for plants for reactive power compensation and for the
provision of instantaneous reserve.
The drastic increase in investment costs compared to
the previous GDP is caused by the change in the scope
of projects and measures as well as the adjustment of
standard and project costs resulting from the overall
economic development.