Page 2 Market Renewal Program – Quarterly Project Status Report, Public, Q1 2024
Key Milestones Completed as of Q1 2024
Factory Acceptance Testing: Market Information Management Infrastructure - Release 1
Site Acceptance Testing: Dispatch Data Management System
Market Rules & Market Manuals - Settlements, Metering & Billing
Internal Manuals - Series 4: Finance/Prudentials
Site Acceptance Testing: Market Power Information System
Site Acceptance Testing: Market Information Management + Energy Market Administrative Tool -
Release 1
Site Acceptance Testing: Market Information Management + Energy Market Interface - Release 1
Solution Development - Market Information Management Infrastructure - Release 2
System Integration Testing: Operational Tools - Part 1
Business Requirement Documents - External Reports
Factory Acceptance Testing: Market Information Management - Release 2
Market Participant Testing - Market Trials Communications & Support Plan
Solution Development - Market Power Information System - Phase 2 - IESO
Market Participant Testing - Market Participant Connectivity Testing & Data Preparation
User Acceptance Testing: Demand Forecast
Site Acceptance Testing: Market Information Management + Energy Market Administrative Tool &
Energy Market Interface - Release 2 (merged milestones)
System Integration Testing: Operational Tools - Part 2
Solution Development - Centralized Alarm Management System
Business Process Integration Testing - Operational Tools