MECHANICS' LIEN LAW OF 1963
Cl. 49Act of Aug. 24, 1963, P.L. 1175, No. 497
AN ACT
To codify, amend, revise and consolidate the laws relating to
mechanics' liens.
TABLE OF CONTENTS
Article I. Short Title
Section 101. Short Title.
Article II. Definitions
Section 201. Definitions.
Article III. Right to Lien
Section 301. Right to Lien; Amount; Subcontractor.
Section 302. Presumption as to Use of Materials.
Section 303. Lien Not Allowed in Certain Cases.
Section 304. Excessive Curtilage.
Section 305. Right to Lien in Case of Noncompletion of Work.
Section 306. Consolidation or Apportionment of Claims.
Section 307. Removal or Detachment of Improvement Subject
to Claim.
Article IV. Waiver of Lien; Effect of Filing
Section 401. Waiver of Lien by Claimant.
Section 402. Waiver by Contractor; Effect on Subcontractor.
Section 403. Release as Waiver.
Section 404. Effect of Credit or Collateral.
Section 405. Right of Owner to Limit Claims to Unpaid
Balance of Contract Price.
Section 406. Right of Subcontractor to Rescind after Notice
of Contract Provisions.
Section 407. Contracts Not Made in Good Faith; Effect.
Article V. Filing and Perfecting Claim; Discharge
of Lien
Section 501. Formal Notice by Subcontractor as Condition
Precedent.
Section 501.1. State Construction Notices Directory.
Section 501.2. Failure to File Notice of Furnishing.
Section 501.3. Notice of Commencement and Notice of Furnishing.
Section 501.4. Notice of Completion for Informational Purposes
Only.
Section 501.5. Notice.
Section 501.6. Prohibition.
Section 502. Filing and Notice of Filing of Claim.
Section 503. Contents of Claim.
Section 504. Amendment of Claim.
Section 505. Procedure for Contesting Claim; Preliminary
Objections.
Section 506. Rule to File Claim.
Section 507. Indexing Claims, Et Cetera.
Section 508. Priority of Lien.
Section 509. Effect of Forfeiture of Leasehold.
Section 510. Discharge of Lien or Reduction of Lien.
Article VI. Duties and Remedies of Owner and Contractor on
Notice of Intention to File or on Filing of
Claim by Subcontractor
Section 601. Owner's Right to Retain Funds of Contractor.
Section 602. Notice to Contractor of Claim.
Section 603. Contractor's Duties on Receipt of Notice.
Section 604. Additional Remedies of Owner.
Article VII. Judgment; Execution; Revival
Section 701. Procedure to Obtain Judgment.
Section 702. Effect of Judgment on Right to Personal Action.
Section 703. Appeal from Judgment.
Section 704. Satisfaction of Claims; Penalty for Failure
to Satisfy.
Section 705. Revival of Judgment.
Section 706. Execution upon Judgment.
Article VIII. Severability and Effective Date
Section 801. Severability.
Section 802. Effective Date.
Article IX. Repealer
Section 901. Specific Repeal.
Section 902. General Repeal.
The General Assembly of the Commonwealth of Pennsylvania
hereby enacts as follows:
ARTICLE I.
SHORT TITLE.
Section 101. Short Title.--This act shall be known and may
be cited as the "Mechanics' Lien Law of 1963."
ARTICLE II
DEFINITIONS
Section 201. Definitions.--The following words, terms and
phrases when used in this act shall have the meaning ascribed
to them in this section, except where the context clearly
indicates a different meaning:
(1) "Improvement" includes any building, structure or other
improvement of whatsoever kind or character erected or
constructed on land, together with the fixtures and other
personal property used in fitting up and equipping the same for
the purpose for which it is intended.
(2) "Property" means the improvement, the land covered
thereby and the lot or curtilage appurtenant thereto belonging
to the same legal or equitable owner reasonably needed for the
general purposes thereof and forming a part of a single business
or residential plant.
(3) "Owner" means an owner in fee, a tenant for life or
years or one having any other estate in or title to property.
(4) "Contractor" means one who, by contract with the owner,
express or implied, erects, constructs, alters or repairs an
improvement or any part thereof or furnishes labor, skill or
superintendence thereto; or supplies or hauls materials,
fixtures, machinery or equipment reasonably necessary for and
actually used therein; or any or all of the foregoing, whether
as superintendent, builder or materialman. The term also
includes an architect or engineer who, by contract with the
owner, express or implied, in addition to the preparation of
drawings, specifications and contract documents also
superintends or supervises any such erection, construction,
alteration or repair.
(5) "Subcontractor" means one who, by contract with the
contractor, or pursuant to a contract with a subcontractor in
direct privity of a contract with a contractor, express or
implied, erects, constructs, alters or repairs an improvement
or any part thereof; or furnishes labor, skill or
superintendence thereto; or supplies or hauls materials,
fixtures, machinery or equipment reasonably necessary for and
actually used therein; or any or all of the foregoing, whether
as superintendent, builder or materialman. The term does not
include an architect or engineer who contracts with a contractor
or subcontractor, or a person who contracts with a materialman
or a person who contracts with a subcontractor not in direct
privity of a contract with a contractor.
(6) "Claimant" means a contractor or subcontractor who has
filed or may file a claim under this act for a lien against
property.
(7) "Materials" means building materials and supplies of
all kinds, and also includes fixtures, machinery and equipment
reasonably necessary to and incorporated into the improvement.
(8) "Completion of the work" means performance of the last
of the labor or delivery of the last of the materials required
by the terms of the claimant's contract or agreement, whichever
last occurs.
(9) "Labor" includes the furnishing of skill or
superintendence.
(10) "Erection and construction" means the erection and
construction of a new improvement or of a substantial addition
to an existing improvement or any adaptation of an existing
improvement rendering the same fit for a new or distinct use
and effecting a material change in the interior or exterior
thereof.
(11) "Alteration and repair" means any alteration or repair
of an existing improvement which does not constitute erection
or construction as defined herein.
(12) "Erection, construction, alteration or repair"
includes:
(a) Demolition, removal of improvements, excavation,
grading, filling, paving and landscaping, when such work is
incidental to the erection, construction, alteration or repair;
(b) Initial fitting up and equipping of the improvement
with fixtures, machinery and equipment suitable to the purposes
for which the erection, construction, alteration or repair was
intended; and
(c) Furnishing, excavating for, laying, relaying, stringing
and restringing rails, ties, pipes, poles and wires, whether
on the property improved or upon other property, in order to
supply services to the improvement.
(13) "Prothonotary" means the prothonotary of the court or
courts of common pleas of the county or counties in which the
improvement is situate.
(14) "Residential property" means property on which there
is or will be constructed a residential building not more than
three stories in height, not including any basement level,
regardless of whether any portion of that basement is at grade
level, or which is zoned or otherwise approved for residential
development on which there is or will be constructed a
residential building not more than three stories in height, not
including any basement level, regardless of whether any portion
of that basement is at grade level, planned residential
development or agricultural use, or for which a residential
subdivision plan or land development plan or planned residential
development plan has received preliminary, tentative or final
approval on which there is or will be constructed a residential
building not more than three stories in height, not including
any basement level, regardless of whether any portion of that
basement is at grade level, pursuant to the act of July 31,
1968 (P.L.805, No.247), known as the "Pennsylvania
Municipalities Planning Code." ((14 amended Aug. 11, 2009,
P.L.l298, No.34)
(15) "Costs of construction" means all costs, expenses and
reimbursements pertaining to erection, construction, alteration,
repair, mandated off-site improvements, government impact fees
and other construction-related costs, including, but not limited
to, costs, expenses and reimbursements in the nature of taxes,
insurance, bonding, inspections, surveys, testing, permits,
legal fees, architect fees, engineering fees, consulting fees,
accounting fees, management fees, utility fees, tenant
improvements, leasing commissions, payment of prior filed or
recorded liens or mortgages, including mechanics liens,
municipal claims, mortgage origination fees and commissions,
finance costs, closing fees, recording fees, title insurance
or escrow fees, or any similar or comparable costs, expenses
or reimbursements related to an improvement made or intended
to be made to the property. For purposes of this definition,
reimbursement includes any such disbursements made to the
borrower, any person acting for the benefit or on behalf of the
borrower or to an affiliate of the borrower. ((15) added July
9, 2014, P.L.1019, No.117)
(16) "Department" means the Department of General Services.
((16) added Oct. 14, 2014, P.L.2494, No.142)
(17) "Directory" means the State Construction Notices
Directory in section 501.1. ((17) added Oct. 14, 2014, P.L.2494,
No.142)
(18) "Searchable project" means a project consisting of the
erection and construction, or alteration or repair, of an
improvement costing a minimum of one million five hundred
thousand dollars ($1,500,000). ((18) added Oct. 14, 2014,
P.L.2494, No.142)
(19) "Construction notice" means the following notices
related to a searchable project:
(i) A Notice of Commencement;
(ii) A Notice of Furnishing;
(iii) A Notice of Completion; or
(iv) A Notice of Nonpayment.
((19) added Oct. 14, 2014, P.L.2494, No.142)
(20) "Searchable project owner" means the owner of record
of real property that is a searchable project. The term shall
include the owner's agent. ((20) added Oct. 14, 2014, P.L.2494,
No.142)
(201 amended June 29, 2006, P.L.210, No.52))
ARTICLE III.
RIGHT TO LIEN.
Section 301. Right to Lien; Amount; Subcontractor.--(a)
General Rule. Except as provided under subsection (b), every
improvement and the estate or title of the owner in the property
shall be subject to a lien, to be perfected as herein provided,
for the payment of all debts due by the owner to the contractor
or by the contractor to any of his subcontractors for labor or
materials furnished in the erection or construction, or the
alteration or repair of the improvement, provided that the
amount of the claim, other than amounts determined by
apportionment under section 306(b) of this act, shall exceed
five hundred dollars ($500).
(b) Subcontractor. A subcontractor does not have the right
to a lien with respect to an improvement to a residential
property if:
(1) the owner or tenant paid the full contract price to the
contractor;
(2) the property is or is intended to be used as the
residence of the owner or subsequent to occupation by the owner,
a tenant of the owner; and
(3) the residential property is a single townhouse or a
building that consists of one or two dwelling units used,
intended or designed to be built, used, rented or leased for
living purposes. For the purposes of this paragraph, the term
"townhouse" shall mean a single-family dwelling unit constructed
in a group of three or more attached units in which each unit
extends from foundation to roof with a yard or public way on
at least two sides.
(301 amended July 9, 2014, P.L.1019, No.117)
Section 302. Presumption as to Use of Materials.--Materials
for use in or upon an improvement placed on or near the property
or delivered to the owner pursuant to a contract shall be
presumed to have been used therein in the absence of proof to
the contrary.
Section 303. Lien Not Allowed in Certain Cases.--
(a) Persons Other Than Contractors or Subcontractors. No
lien shall be allowed in favor of any person other than a
contractor or subcontractor, as defined herein, even though
such person furnishes labor or materials to an improvement.
(b) Public Purpose. No lien shall be allowed for labor or
materials furnished for a purely public purpose.
(c) Conveyance Prior to Lien. If the property be conveyed
in good faith and for a valuable consideration prior to the
filing of a claim for alterations or repairs, the lien shall
be wholly lost.
(d) Leasehold Premises. No lien shall be allowed against
the estate of an owner in fee by reason of any consent given
by such owner to a tenant to improve the leased premises unless
it shall appear in writing signed by such owner that the
erection, construction, alteration or repair was in fact for
the immediate use and benefit of the owner.
(e) Security Interests. No lien shall be allowed for that
portion of a debt representing the contract price of any
materials against which the claimant holds or has claimed a
security interest under the Pennsylvania Uniform Commercial
Code or to which he has reserved title or the right to reacquire
title.
Section 304. Excessive Curtilage.--Where an owner objects
that a lien has been claimed against more property than should
justly be included therein, the court upon petition may, after
hearing by deposition or otherwise, limit the boundaries of the
property subject to the lien. Failure to raise this objection
preliminarily shall not be a waiver of the right to plead the
same as a defense thereafter.
Section 305. Right to Lien in Case of Noncompletion of
Work.--Except in case of destruction by fire or other casualty,
where, through no fault of the claimant, the improvement is not
completed, the right to lien shall nevertheless exist.
Section 306. Consolidation or Apportionment of Claims.--
(a) Consolidation of Claims. Where a debt is incurred for
labor or materials furnished continuously by the same claimant
for work upon a single improvement but under more than one
contract, the claimant may elect to file a single claim for the
entire debt. In such case, "completion of the work" shall not
be deemed to occur with respect to any of the contracts until
it has occurred with respect to all of them.
(b) Apportionment of Claims. Where a debt is incurred for
labor or materials furnished by the same claimant for work upon
several different improvements which do not form all or part
of a single business or residential plant, the claimant shall
file separate claims with respect to each such improvement,
with the amount of each claim determined by apportionment of
the total debt to the several improvements, and in such case,
the amount of each separate claim may be less than five hundred
dollars ($500), provided that the total debt exceeds five
hundred dollars ($500). In no other case shall an apportioned
claim be allowed.
Section 307. Removal or Detachment of Improvement Subject
to Claim.--
(a) Removal Prohibited; Effect. No improvement subject to
the lien of a claim filed in accordance with this act shall be
removed or detached from the land except pursuant to title
obtained at a judicial sale or by one owning the land and not
named as a defendant. Any improvement otherwise removed shall
remain liable to the claim filed, except in the hands of a
purchaser for value.
(b) Restraint of Removal by Court. The court may on petition
restrain the removal of the improvement in accordance with the
Pennsylvania Rules of Civil Procedure governing actions to
prevent waste.
ARTICLE IV.
WAIVER OF LIEN; EFFECT OF FILING.
Section 401. Waiver of Lien by Claimant.--
(a) Residential Property.
A contractor or subcontractor may waive his right to file a
claim against residential property by a written instrument
signed by him or by any conduct which operates equitably to
estop such contractor from filing a claim.
(b) Nonresidential Buildings.
(1) Except as provided in subsection (a), a waiver by a
contractor of lien rights is against public policy, unlawful
and void unless given in consideration for payment for the work,
services, materials or equipment provided and only to the extent
that such payment is actually received.
(2) Except as provided in subsection (a), a waiver by a
subcontractor of lien rights is against public policy, unlawful
and void, unless given in consideration for payment for the
work, services, materials or equipment provided and only to the
extent that such payment is actually received, or unless the
contractor has posted a bond guaranteeing payment for labor and
materials provided by subcontractors.
(401 amended Aug. 11, 2009, P.L.298, No.34)
Section 402. Waiver by Contractor; Effect on
Subcontractor.--
(a) General Rule. To the extent that lien rights may be
validly waived by a contractor or subcontractor under section
401(a) or where the contractor has posted a bond under section
401(b)(2), a written contract between the owner and a
contractor, or a separate written instrument signed by the
contractor, which provides that no claim shall be filed by
anyone, shall be binding: but the only admissible evidence
thereof, as against a subcontractor, shall be proof of actual
notice thereof to him before any labor or materials were
furnished by him; or proof that such contract or separate
written instrument was filed in the office of the prothonotary
prior to the commencement of the work upon the ground or within
ten (10) days after the execution of the principal contract or
not less than ten (10) days prior to the contract with the
claimant subcontractor, indexed in the name of the contractor
as defendant and the owner as plaintiff and also in the name
of the contractor as plaintiff and the owner as defendant. The
only admissible evidence that such a provision has,
notwithstanding its filing, been waived in favor of any
subcontractor, shall be a written agreement to that effect
signed by all those who, under the contract, have an adverse
interest to the subcontractor's allegation.((a) amended Aug.
11, 2009, P.L.298, No.34)
(b) Electronic Indexing. Notwithstanding the indexing
requirements of subsection (a) in offices of the prothonotary
in which such a written contract between the owner and
contractor or separate written instrument is indexed
electronically by means of a computer system or similar system
such that the names of the contractor and owner are
electronically retrievable regardless of whether the parties
are designated as plaintiff or defendant, the contract or
separate written instrument filed with the office of the
prothonotary under subsection (a) may be indexed in the name
of the contractor as defendant and the owner as plaintiff or
in the name of the contractor as plaintiff and the owner as
defendant.
(402 amended June 29, 2006, P.L.210, No.52)
Section 403. Release as Waiver.--A release signed by the
claimant shall not operate as a waiver of the right to file a
claim for labor or materials subsequently furnished, unless it
shall appear thereby that such was the express intent of the
party signing the same.
Section 404. Effect of Credit or Collateral.--The giving
of credit or the receipt of evidence of indebtedness or
collateral otherwise than as provided in section 303(e) shall
not operate to waive the right to file a claim, but where credit
is given, no voluntary proceedings shall be taken by the
claimant to enforce the lien until the credit period has
expired.
Section 405. Right of Owner to Limit Claims to Unpaid
Balance of Contract Price.--Where the claims of subcontractors
exceed in the aggregate the unpaid balance of the contract price
specified in the contract between the owner and the contractor,
then if the subcontractor has actual notice of the total amount
of said contract price and of its provisions for the time or
times for payment thereof before any labor or materials were
furnished by him, or if such contract or the pertinent
provisions thereof were filed in the office of the prothonotary
in the time and manner provided in section 402, each claim
shall, upon application of the owner, be limited to its pro-rata
share of the contract price remaining unpaid, or which should
have remained unpaid, whichever is greatest in amount at the
time notice of intention to file a claim was first given to the
owner, such notice inuring to the benefit of all claimants.
(405 amended June 29, 2006, P.L.210, No.52)
Section 406. Right of Subcontractor to Rescind after Notice
of Contract Provisions.--Any provisions of a contract between
the owner and the contractor, which reduce or impair the rights
and remedies of a subcontractor or which postpone the time for
payment by the owner to the contractor for a period exceeding
four (4) months after completion of the work, shall be grounds
for recision by the subcontractor of his contract with the
contractor, unless such subcontractor was given actual notice
thereof prior to the time of the making of his contract with
the contractor, or the contract or the pertinent provisions
thereof were filed in the office of the prothonotary in the
time and manner provided by section 402. Such recision shall
not impair the right of the subcontractor to recover by lien
or otherwise for work completed prior thereto.
Section 407. Contracts Not Made in Good Faith; Effect.--A
contract for the improvement made by the owner with one not
intended in good faith to be a contractor shall have no legal
effect except as between the parties thereto, even though
written, signed and filed as provided herein, but such
contractor, as to third parties shall be treated as the agent
of the owner.
ARTICLE V.
FILING AND PERFECTING CLAIM; DISCHARGE OF LIEN.
Section 501. Formal Notice by Subcontractor as Condition
Precedent.--
(a) (Deleted by amendment).
(b) (Deleted by amendment).
(b.1) Time Period of Formal Notice. No claim by a
subcontractor, whether for erection or construction or for
alterations or repairs, shall be valid unless, at least thirty
(30) days before the same is filed, he shall have given to the
owner a formal written notice of his intention to file a claim,
except that such notice shall not be required where the claim
is filed pursuant to a rule to do so as provided by section
506.
(c) Contents of Formal Notice. The formal notice shall
state:
(1) the name of the party claimant;
(2) the name of the person with whom he contracted;
(3) the amount claimed to be due;
(4) the general nature and character of the labor or
materials furnished;
(5) the date of completion of the work for which his claim
is made;
(6) a brief description sufficient to identify the property
claimed to be subject to the lien.
(d) Service of Notice. The notice provided by this section
may be served by first class, registered or certified mail on
the owner or his agent or by an adult in the same manner as a
writ of summons in assumpsit, or if service cannot be so made
then by posting upon a conspicuous public part of the
improvement.
(501 amended June 29, 2006, P.L.210, No.52)
Section 501.1. State Construction Notices Directory.--
(a) Directory. The department shall provide for an Internet
website to be known as the State Construction Notices Directory
to serve as a standardized Statewide system for filing
construction notices.
(b) Operational Date. The directory shall be operational
by December 31, 2016. The department may establish a later
effective date if it provides sufficient reasons for the delay
in the implementation of the directory in a notice to the
chairman and minority chairman of the Labor and Industry
Committee of the Senate and the chairman and minority chairman
of the Labor and Industry Committee of the House of
Representatives.
(c) Notification. No later than one hundred twenty (120)
days after the implementation of the directory, the department
shall publish notice in the Pennsylvania Bulletin advising the
public of implementation of the directory and instructions on
its use. The department shall place the notice and instructions
on its Internet website and take other reasonable measures to
inform the general public and the construction industry of the
directory and its purpose.
(d) Fees. The following shall apply:
(1) The department shall establish fees for notices filed
by the searchable project owner.
(2) Fees under paragraph (1) may not in the aggregate exceed
the amount reasonably necessary to implement, operate and
maintain the directory.
(e) Publishing of Notices. The directory shall:
(1) Make Notices of Commencement filed under section
501.3(a) available for a searchable project in a job-site
specific format. A unique identifying number shall be assigned
to each Notice of Commencement that is filed. A notice under
this paragraph shall be searchable by searchable project owner
name, contractor name, property address and unique identifying
number.
(2) Provide copies of the filings of Notice of Furnishing
under section 501.3(b) to a searchable project owner who files
a Notice of Commencement under section 501.3(a).
(3) Provide certified hard copy printing of electronic
receipts upon request for a filing under section 501.3 of a
Notice of Commencement or Notice of Furnishing. The certified
hard copy shall include the date, time and content of the
individual filing.
(4) List all Notices of Furnishing and Notices of Completion
filed with respect to a particular Notice of Commencement.
(5) Provide a verification process to allow persons filing
required notices or requests for notices in the directory to
confirm the proper indexing and linkage of their filings.
(f) Index. The directory must be primarily indexed by
county.
(501.1 added Oct. 14, 2014, P.L.2494, No.142)
Compiler's Note: See section 4 of Act 142 of 2014 in the
appendix to this act for special provisions relating to
designation of operational date.
Section 501.2. Failure to File Notice of Furnishing.--A
contract for a searchable project shall include written notice
that failure to file a Notice of Furnishing under section
501.3(b) will result in the loss of lien rights. The notice
shall be as follows:
A subcontractor that fails to file a Notice of Furnishing
on the Department of General Services' publicly accessible
Internet website as required by the act of August 24, 1963
(P.L.1175, No.497), known as the Mechanics' Lien Law of 1963,
may forfeit the right to file a mechanics lien. It is
unlawful for a searchable project owner, searchable project
owner's agent, contractor or subcontractor to request,
suggest, encourage or require that a subcontractor not file
the required notice as required by the Mechanics' Lien Law
of 1963.
(501.2 added Oct. 14, 2014, P.L.2494, No.142)
Compiler's Note: Section 3 of Act 142 of 2014, which added
section 501.2, provided that the notice provisions of
section 501.2 shall apply to projects commenced on or
after the operational date of the directory.
Section 501.3. Notice of Commencement and Notice of
Furnishing.--
(a) Notice of Commencement.
(1) Prior to the commencement of labor, work or the
furnishing of materials for a searchable project that may give
rise to a mechanics' lien under this act, the searchable project
owner or agent of the searchable project owner may file a Notice
of Commencement with the directory.
(2) A contractor may act as agent for the searchable project
owner and file a Notice of Commencement for the searchable
project owner of a searchable project if specifically authorized
by contract and the searchable project owner assumes
responsibility for the contractor's actions.
(3) The notice must include the following:
(i) Full name, address and e-mail address of the contractor.
(ii) Full name and location of the searchable project.
(iii) The county in which the searchable project is located.
(iv) The legal description of the property upon which the
improvements are being made, including the tax identification
number of each parcel included in the searchable project.
(v) Full name, address and e-mail address of the searchable
project owner of record of the property and the searchable
project being constructed.
(vi) If applicable, the full name, address and e-mail
address of a surety for the performance and payment bonds and
the bond numbers.
(vii) The unique identifying number that is assigned to the
Notice of Commencement pursuant to section 501.1(e)(1).
(4) The searchable project owner shall also conspicuously
post a copy of the Notice of Commencement at the site of a
searchable project before physical work commences on the project
to include the unique identifying number assigned under section
501.1(e)(1). The searchable project owner shall take reasonable
measures to ensure that the Notice of Commencement remains
posted at the searchable project site until completion of the
project. For the purposes of this paragraph, the term
"reasonable measures" means the reposting of notice by the
searchable project owner within forty-eight (48) hours after
becoming aware of or being notified verbally, in writing or by
e-mail that the notice is not posted.
(5) The searchable project owner and the contractor shall
make reasonable efforts to ensure that the Notice of
Commencement is made part of contract documents provided to all
subcontractors awarded work on the searchable project.
(b) Notice of Furnishing. A subcontractor that performs
work or services or provides material in furtherance of a
searchable project shall comply with the following if a Notice
of Commencement has been filed and posted in accordance with
subsection (a):
(1) File a Notice of Furnishing with the directory within
forty-five (45) days after first performing work or services
at the job site or first providing materials to the job site
in connection with the searchable project.
(2) The notice under paragraph (1) must contain the
following:
(i) A general description of the labor or materials
furnished.
(ii) Full name and address of the person supplying the
services or items under subparagraph (i).
(iii) Full name and address of the person that contracted
for the services or items under subparagraph (i).
(iv) A description sufficient to identify the searchable
project, based on the description in the Notice of Commencement.
(3) The notice under paragraph (1) must be substantially
in the following form:
Notice of Furnishing
To:..................................
(Name of searchable project owner)
.....................................
(Address of searchable project owner)
(Notice of Commencement Number)
Please take notice that the undersigned is performing
certain work or labor or furnishing certain materials
to........................(Name and address of other
contracting party) in connection with the improvement to the
real property located at........................ The labor,
work or materials were performed or furnished first, or will
be furnished first, on.........(date).
............................
(Name and Address of Lien Claimant)
By
(Name and capacity of party signing for lien claimant)
............................
(Address of Signing Party)
............................
(Date)
(c) Construction. A subcontractor that fails to
substantially comply with this section forfeits the right to
file a lien claim.
(501.3 added Oct. 14, 2014, P.L.2494, No.142)
Compiler's Note: Section 3 of Act 142 of 2014, which added
section 501.3, provided that the notice provisions of
section 501.3 shall apply to projects commenced on or
after the operational date of the directory.
Section 501.4. Notice of Completion for Informational
Purposes Only.--
(a) General Rule. Within forty-five (45) days of the actual
completion of work on a searchable project, a searchable project
owner may file a Notice of Completion in the directory to be
indexed with the original Notice of Commencement. The notice
shall be transmitted via the directory to all subcontractors
who have filed Notices of Furnishing. For the purposes of this
paragraph, the term "actual completion of work" shall mean the
following:
(1) The issuance of an occupancy permit to the searchable
project owner, or his agent, and the acceptance by the
searchable project owner, or his agent, of the work accompanied
by cessation of all work on the searchable project; or
(2) The cessation of all work on the searchable project for
thirty (30) consecutive days, provided that work is not resumed
under the same contract.
(b) Nonpayment. Subcontractors who have not received full
payment for their work, or for goods or services, on a
searchable project may file a Notice of Nonpayment with the
searchable project owner or the searchable project owner's agent
or the subcontractor in the directory for informational purposes
only. The failure to file a Notice of Nonpayment by a
subcontractor shall not be construed to affect or limit their
rights under this act. Filing of a Notice of Nonpayment shall
not relieve a subcontractor from complying with other written
notice requirements under this act.
(c) Court. A Notice of Completion shall not be considered
by a court in determining compliance with timing requirements
under this act or in determining the completion date for a
timing purpose, including limitation periods or warranty
obligations.
(d) Effect. The filing of a Notice of Completion is purely
precatory and is not dispositive of any relationship among the
parties.
(501.4 added Oct. 14, 2014, P.L.2494, No.142)
Compiler's Note: Section 3 of Act 142 of 2014, which added
section 501.4, provided that the notice provisions of
section 501.4 shall apply to projects commenced on or
after the operational date of the directory.
Section 501.5. Notice.--
(a) Notification. The directory shall provide notification
of a filing of a notice under sections 501.3 and 501.4 to a
person who requests notification of the filing of a notice for
a searchable project.
(b) Requests. A person who requests the directory to provide
the person with official copies of notification of the filing
of a notice for a searchable project shall:
(1) provide an e-mail address, mailing address or telefax
number to which notification may be sent; and
(2) be responsible for the accuracy of the e-mail address,
mailing address or telefax number.
(c) Requirements. A person shall be considered to have
requested notification under this section if the person files,
with respect to the same searchable project that relates to the
required notice, any of the following:
(1) A Notice of Commencement.
(2) A Notice of Furnishing.
(3) A Notice of Completion.
(d) Notification requirements. Notification requirements
shall be fulfilled by the directory by sending the official
notification to the e-mail address, mailing address or telefax
number that the person provides.
(e) Official notification. A person filing a Notice of
Commencement, Notice of Furnishing, Notice of Completion or
related notice must verify the accuracy of information entered
into the directory, regardless of whether the person files
electronically, by alternate means or through a third party.
(f) Information. Each notice or other document submitted
to the directory must contain:
(1) The name of the county in which the searchable project
property to which the notice or other document applies is
located.
(2) The tax identification number of each parcel included
in the project property.
(3) The number of the building permit for the searchable
project on the project property.
(501.5 added Oct. 14, 2014, P.L.2494, No.142)
Compiler's Note: Section 3 of Act 142 of 2014, which added
section 501.5, provided that the notice provisions of
section 501.5 shall apply to projects commenced on or
after the operational date of the directory.
Section 501.6. Prohibition.--
(a) Unlawful Acts. It shall be unlawful for a searchable
project owner or the searchable project owner's agent, a
contractor or subcontractor to suggest, request, encourage or
require that a subcontractor not file a Notice of Furnishing
as a condition of entering into, continuing, receiving or
maintaining a contract for work or furnishing of materials on
a searchable project. A person that violates this subsection
commits a misdemeanor of the second degree.
(b) Lien by subcontractor. A subcontractor has the right
to file a lien for the work and services performed and the
materials furnished under this act, irrespective of compliance
with section 501.3(b), if the subcontractor proves that the
failure to comply with section 501.3(b) was directly the result
of a searchable project owner, the searchable project owner's
agent or the contractor violating subsection (a).
(c) Cause of Action. A subcontractor shall have a civil
cause of action if the subcontractor proves that failure to
comply with section 501.3(b) was the result of a searchable
project owner or searchable project owner's agent, or a
contractor or subcontractor, violating subsection (a) in order
to recover damages for any loss or injury sustained as a result
of the violation from a person who commits a violation. The
civil cause of action shall only be applied to the entity that
violates subsection (a). A court of competent jurisdiction may
award to the subcontractor actual damages arising from the
violation, reasonable attorneys fees and court costs.
(d) Abuse. A person abuses the directory if the person files
a notice in the directory:
(1) Without a good faith reason to do so.
(2) With the intent to exact more payment than is due from
the searchable project owner or other party.
(3) To obtain an unjustified advantage or benefit.
(e) Damages. A person who abuses the directory under
subsection (d) shall be liable for the amount of actual damages
or $2,000, whichever is greater.
(501.6 added Oct. 14, 2014, P.L.2494, No.142)
Section 502. Filing and Notice of Filing of Claim.--
(a) Perfection of Lien. To perfect a lien, every claimant
must:
(1) file a claim with the prothonotary as provided by this
act within six (6) months after the completion of his work; and
(2) serve written notice of such filing upon the owner
within one (1) month after filing, giving the court, term and
number and date of filing of the claim. An affidavit of service
of notice, or the acceptance of service, shall be filed within
twenty (20) days after service setting forth the date and manner
of service. Failure to serve such notice or to file the
affidavit or acceptance of service within the times specified
shall be sufficient ground for striking off the claim.
(b) Venue; Property in More Than One County. Where the
improvement is located in more than one county, the claim may
be filed in any one or more of said counties, but shall be
effective only as to the part of the property in the county in
which it has been filed.
(c) Manner of Service. Service of the notice of filing of
claim shall be made by an adult in the same manner as a writ
of summons in assumpsit, or if service cannot be so made then
by posting upon a conspicuous public part of the improvement.
(502 amended June 29, 2006, P.L.210, No.52)
Section 503. Contents of Claim.--The claim shall state:
(1) the name of the party claimant, and whether he files
as contractor or subcontractor;
(2) the name and address of the owner or reputed owner;
(3) the date of completion of the claimant's work;
(4) if filed by a subcontractor, the name of the person
with whom he contracted, and the dates on which preliminary
notice, if required, and of formal notice of intention to file
a claim was given;
(5) if filed by a contractor under a contract or contracts
for an agreed sum, an identification of the contract and a
general statement of the kind and character of the labor or
materials furnished;
(6) in all other cases than that set forth in clause (5)
of this section, a detailed statement of the kind and character
of the labor or materials furnished, or both, and the prices
charged for each thereof;
(7) the amount or sum claimed to be due; and
(8) such description of the improvement and of the property
claimed to be subject to the lien as may be reasonably necessary
to identify them.
Section 504. Amendment of Claim.--A claim may be amended
from time to time without prejudice to intervening rights by
agreement of the parties or by leave of court, except that no
amendment shall be permitted after the time for filing a claim
has expired which undertakes to:
(1) substitute a different property than that described in
the claim; or
(2) substitute a different party with whom the claimant
contracted; or
(3) increase the aggregate amount of the claim.
Section 505. Procedure for Contesting Claim; Preliminary
Objections.--Any party may preliminarily object to a claim upon
a showing of exemption or immunity of the property from lien,
or for lack of conformity with this act. The court shall
determine all preliminary objections. If an issue of fact is
raised in such objections, the court may take evidence by
deposition or otherwise. If the filing of an amended claim is
allowed, the court shall fix the time within which it shall be
filed. Failure to file an objection preliminarily shall not
constitute a waiver of the right to raise the same as a defense
in subsequent proceedings.
Section 506. Rule to File Claim.--
(a) Entry of Rule; Effect. At any time after the completion
of the work by a subcontractor, any owner or contractor may
file a rule or rules, as of course, in the court in which said
claim may be filed requiring the party named therein to file
his claim within thirty (30) days after notice of said rule or
be forever barred from so doing. The rule shall be entered by
the prothonotary upon the judgment index and in the mechanics'
lien docket. Failure to file a claim within the time specified
shall operate to wholly defeat the right to do so. If a claim
be filed, it shall be entered as of the court, term and number
of the rule to file the same.
(b) Effect of Claim Filed by Subcontractor. Where a claim
is filed by a subcontractor in response to such rule, the owner
may give written notice thereof to the contractor in the manner
set forth by section 602 of this act, and upon the giving of
such notice the owner may avail himself of the remedies provided
by sections 601 and 604 of this act and the contractor shall
be subject to the duties set forth by section 603 of this act.
Compiler's Note: Pennsylvania Rule of Civil Procedure No.
1068(a), adopted March 11, 1991, provided that section
506 shall not be deemed suspended or affected by the
rules of civil procedure.
Section 507. Indexing Claims, Et Cetera.--The prothonotary
shall enter the claim, verdict and judgment upon the judgment
index and mechanics' lien docket against the owner. When a
claim, verdict or judgment is stricken, reversed or satisfied,
or the name of a defendant is stricken, or an action upon the
claim to reduce it to judgment is discontinued, or judgment is
entered thereon in favor of the defendant, a note shall be made
on the judgment index.
Section 508. Priority of Lien.--The lien of a claim filed
under this act shall take effect and have priority as follows:
(a) Except as set forth in subsection (c), in the case of
the erection or construction of an improvement, as of the date
of the visible commencement upon the ground of the work of
erecting or constructing the improvement.
(b) Except as set forth in subsection (c), in the case of
the alteration or repair of an improvement, as of the date of
the filing of the claim.
(c) Any lien obtained under this act by a contractor or
subcontractor shall be subordinate to the following:
(1) A purchase money mortgage as defined in 42 Pa.C.S. §
8141(1) (relating to time from which liens have priority).
(2) An open-end mortgage as defined in 42 Pa.C.S. § 8143(f)
(relating to open-end mortgages), where at least sixty percent
(60%) of the proceeds are intended to pay or are used to pay
all or part of the costs of construction. ((c) amended July 9,
2014, P.L.1019, No.117)
(508 amended June 29, 2006, P.L.210, No.52)
Section 509. Effect of Forfeiture of Leasehold.--The lien
of every claim shall bind only the interest of the party named
as owner of the property at the time of the contract or acquired
subsequently by him, but no forfeiture or surrender of a
leasehold or tenancy, whether before or after the filing of the
claim, shall operate to prejudice its lien against the fixtures,
machinery or other similar property.
Section 510. Discharge of Lien or Reduction of Lien.--(Hdg.
amended July 9, 2014, P.L.1019, No.117)
(a) Cash Deposit. Any claim filed hereunder shall, upon
petition of the owner or any party in interest, be discharged
as a lien against the property whenever a sum equal to the
amount of the claim shall have been deposited with the court
in said proceedings for application to the payment of the amount
finally determined to be due.
(b) Pro-rata Allocation. In any case where the claim or
claims are limited in the manner and to the extent provided in
section 405, the owner may deposit with the court in separate
proceedings a sum equal to the total allowable amount of said
claims determined in accordance with said section, whereupon
the court, on petition of such owner, shall order all of said
claims discharged as liens against the property, and the sum
so deposited applied pro rata to the payment thereof in the
amounts finally determined to be due.
(c) Refund of Excess. Any excess of funds paid into court
as aforesaid, over the amount of the claim or claims determined
and paid therefrom, shall be refunded to the owner or party
depositing same upon application for the same.
(d) Security in Lieu of Cash. In lieu of the deposit of any
such sum or sums, approved security may be entered in such
proceedings in double the amount of the required deposit, or
in such lesser amount as the court shall approve, which,
however, shall in no event be less than the full amount of such
required deposit; and the entry of such security shall entitle
the owner to have such liens discharged to the same effect as
though the required sums had been deposited in court as
aforesaid.
(e) Authority of Court. The court, upon petition filed by
any party, and after notice and hearing, may upon cause shown:
(1) require the increase or decrease of any deposit or
security;
(2) strike off security improperly filed;
(3) permit the substitution of security and enter an
exoneration of security already given.
(f) Residential Property.
(1) A claim filed under this act with respect to an
improvement to a residential property subject to section 301(b)
shall, upon a court order issued in response to a petition or
motion to the court by the owner or a party in interest, be
discharged as a lien against the property when the owner or
tenant has paid the full contract price to the contractor.
(2) Where the owner or tenant has paid a sum to the
contractor which is less than the sum of the full contract
price, a claim filed under this act with respect to an
improvement to a residential property subject to section 301(b)
shall, upon a court order issued in response to a petition or
motion to the court by the owner or a party in interest, cause
the lien to be reduced to the amount of the unpaid contract
price owed by the owner or tenant to the contractor.
((f) added July 9, 2014, P.L.1019, No.117)
ARTICLE VI.
DUTIES AND REMEDIES OF OWNER AND CONTRACTOR ON
NOTICE OF INTENTION TO FILE OR ON FILING OF
CLAIM BY SUBCONTRACTOR.
Section 601. Owner's Right to Retain Funds of
Contractor.--An owner who has been served with a notice of
intention to file or a notice of the filing of a claim by a
subcontractor may retain out of any moneys due or to become due
to the contractor named therein, a sum sufficient to protect
the owner from loss until such time as the claim is finally
settled, released, defeated or discharged.
Section 602. Notice to Contractor of Claim.--
(a) An owner served with a notice as provided by section
601 may, and if he has retained any funds due the contractor
shall, give written notice thereof to the contractor named.
(b) The notice shall state:
(1) the name of the subcontractor, the amount of the claim
and the amount withheld, if any, by the owner;
(2) that unless the contractor within thirty (30) days from
service of the notice settles, undertakes to defend, or secures
against the claim as provided by section 603, the owner may
avail himself of the remedies provided by section 604.
(c) The notice may be given by the owner or his agent to
the contractor personally, or to the contractor's manager,
executive or principal officer or other agent, or if none of
these persons can be found, by sending a copy of the notice by
first class, registered or certified mail to the contractor at
his last known office address.
Section 603. Contractor's Duties on Receipt of Notice.--Upon
service of the notice provided by section 602, the contractor
shall within thirty (30) days from the contractor's receipt of
notice:
(1) settle or discharge the claim of the subcontractor and
furnish to the owner a written copy of a waiver, release or
satisfaction thereof, signed by the claimant; or
(2) agree in writing to undertake to defend against said
claim, and if the owner has not retained sufficient funds to
protect him against loss, furnish the owner additional approved
security to protect the owner from loss in the event the defense
should be abandoned by the contractor or should not prevail;
or
(3) furnish to the owner approved security in an amount
sufficient to protect the owner from loss on account of said
claim.
Section 604. Additional Remedies of Owner.--Should the
contractor fail to settle, discharge or defend or secure against
the claim, as provided by this act, the owner may:
(1) pay the claim of the subcontractor, upon which payment
the owner shall be subrogated to the rights of the subcontractor
against the contractor together with any instrument or other
collateral security held by the subcontractor for the payment
thereof; or
(2) undertake a defense against said claim in which case
the contractor shall be liable to the owner for all costs,
expenses and charges incurred in such defense, including
reasonable attorneys' fees, whether said defense be successful
or not, but the undertaking of such defense shall not affect
the right of the owner to retain funds of the contractor under
section 601 until the subcontractor's claim is finally defeated
or discharged.
ARTICLE VII.
JUDGMENT; EXECUTION; REVIVAL.
Section 701. Procedure to Obtain Judgment.--
(a) Practice and Procedure. The practice and procedure to
obtain judgment upon a claim filed shall be governed by the
Rules of Civil Procedure promulgated by the Supreme Court.
(b) Time for Commencing Action. An action to obtain judgment
upon a claim filed shall be commenced within two (2) years from
the date of filing unless the time be extended in writing by
the owner.
(c) Venue; Property in More Than One County. Where a claim
has been filed in more than one county as provided by section
502(b), proceedings to obtain judgment upon all the claims may
be commenced in any of the counties and the judgment shall be
res adjudicata as to the merits of the claims properly filed
in the other counties. The judgment may be transferred to such
other county by filing of record a certified copy of the docket
entries in the action and a certification of the judgment and
amount, if any. The prothonotary of the court to which the
judgment has been transferred shall forthwith index it upon the
judgment index and enter it upon the mechanics' lien docket.
(d) Limitation on Time of Obtaining Judgment. A verdict
must be recovered or judgment entered within five (5) years
from the date of filing of the claim. Final judgment must be
entered on a verdict within five (5) years. If a claim is not
prosecuted to verdict or judgment, as provided above, the claim
shall be wholly lost: Provided, however, That in either case,
if a complaint has been or shall be filed in the cause and if
the cause has been or shall be at issue, all time theretofore
or thereafter consumed in the presentation and disposition of
all motions and petitions of defendants, substituted defendants
and intervenors in the cause, and in any appeal or appeals from
any order in the cause, from the date of perfection of such
appeal to the date of return of the certiorari from the
appellate court to the court of common pleas, shall be excluded
in the computation of the five (5) year period herein provided.
((d) amended Dec. 28, 1972, P.L.1640, No.343)
(e) Defense to Action on Claim. A setoff arising from the
same transaction or occurrence from which the claim arose may
be pleaded but may not be made the basis of a counterclaim.
Section 702. Effect of Judgment on Right to Personal
Action.--Nothing in this act shall alter or affect the right
of a claimant to proceed in any other manner for the collection
of his debt.
Section 703. Appeal from Judgment.--From any judgment, order
or decree entered by the court of common pleas under the
provisions of this act or from any refusal to open a judgment
entered by default, an appeal may be taken.
(703 repealed in part June 3, 1971, P.L.118, No.6)
Section 704. Satisfaction of Claims; Penalty for Failure
to Satisfy.--It shall be the duty of a claimant upon payment,
satisfaction or other discharge of the claim, verdict or
judgment to enter satisfaction thereof upon the record upon
payment of the costs of same. Upon failure to do so within
thirty (30) days after a written request to satisfy, the court
upon petition of any party in interest may order the claim,
verdict or judgment satisfied and the claimant shall be subject
to a penalty in favor of the party aggrieved in such sum as the
court in the petition proceedings shall determine to be just,
but not exceeding the amount of claim.
Section 705. Revival of Judgment.--Judgment upon a claim
shall be revived within each recurring five-year period. The
practice and procedure to revive judgment shall be governed by
the Judgment Lien Law of 1947, as now in force or hereafter
amended, and the Rules of Civil Procedure promulgated by the
Supreme Court, but the lien of the revived judgment shall, as
in the case of the original judgment, be limited to the liened
property.
Section 706. Execution upon Judgment.--
(a) Judgment Essential to Execution. No execution shall
issue against the property subject to a claim except after
judgment shall have been obtained upon the claim, and within
five (5) years from the date of such judgment or a revival
thereof.
(b) Conformity to Rules of Civil Procedure. The practice
and procedure relating to execution shall be governed by the
Pennsylvania Rules of Civil Procedure relating to execution.
(c) Division of Tract. Where only a part of a single tract
is subject to the lien of a mechanic's claim, and such part
cannot be sold without prejudice or injury to the whole, the
court on petition of the owner, claimant or any person in
interest may order the entire tract sold and shall equitably
distribute the proceeds of sale according to the relative value
of the part bound by and that free of the claim. The court may
determine the matter itself and for that purpose may receive
evidence by deposition or otherwise, or may appoint an auditor
to hear the evidence and report to the court.
ARTICLE VIII.
SEVERABILITY AND EFFECTIVE DATE.
Section 801. Severability.--If any provision of this act,
or the application thereof to any person or circumstance is
held invalid, the remainder of this act, and the application
of such provision to other persons or circumstances, shall not
be affected thereby and to this end the provisions of this act
are declared to be severable.
Section 802. Effective Date.--This act shall take effect
on the first day of January, 1964, but shall not apply to liens
filed prior to said date except with respect to the practice
and procedure prescribed by Article VII of this act.
ARTICLE IX.
REPEALER.
Section 901. Specific Repeal.--The following act is repealed
absolutely.
The act of June 4, 1901 (P.L.431), entitled "An act defining
the rights and liabilities of parties to, and regulating the
effect of, contracts for work and labor to be done, and labor
or materials to be furnished, to any building, bridge, wharf,
dock, pier, bulkhead, vault, subway, tramway, toll-road,
conduit, tunnel, mine, coal-breaker, flume, pump, screen, tank,
derrick, pipe-line, aqueduct, reservoir, viaduct, telegraph,
telephone, railway or railroad line; canal, millrace; works for
supplying water, heat, light, power, cold air, or any other
substance furnished to the public; well for the production of
gas, oil or other volatile or mineral substance; or other
structure or improvement, or whatsoever kind or character the
same may be; providing remedies for the recovery of debts due
by reason of such contracts, and repealing, consolidating and
extending existing laws in relation thereto."
Section 902. General Repeal.--All other acts and parts of
acts are repealed in so far as they are inconsistent herewith.
APPENDIX
-------
Supplementary Provisions of Amendatory Statutes
-------
2014, OCTOBER 14, P.L.2494, NO.142
Section 4. The Department of General Services may
designate the operational date of the State Construction Notices
Directory under section 501.1(b). If the Department of General
Services designates an operational date other than December 31,
2016, it shall transmit the designation to the Legislative
Reference Bureau for publication in the Pennsylvania Bulletin.
Compiler's Note: Act 142 amended or added sections 201,
501.1, 501.2, 501.3, 501.4, 501.5 and 501.6 of Act 497.